| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2 | 107.88 | 81.5 | 75.55 | ||||||||||||||
| 1 | KALIMPONG | Kalimpong-I | Neorakhola W/S & Mtc.Div. | PWSS SCHEME FROM SISNEY KHOLA TO UPPER AND LOWER KAMBAL & DINGALI GAON , SM/09613 | New | Piped Water Supply Scheme from Sisney Khola to Upper and Lower Kambal and Dingali Gaon in Yangmakum G.P. Block l, Kalimpong under Jal Swapno Programme within Kalimpong District | Assistant Engineer I | Junior Engineer IV | ORD/000143/2021-2022 | 754/NKWSMD | 28/02/2022 | 90 | MR. DAWA LAMA | 107.34 | 81.50 | 75.93 | 80 |
| 2 | KALIMPONG | Kalimpong-I | Neorakhola W/S & Mtc.Div. | PWSS SCHEME FROM SISNEY KHOLA TO UPPER AND LOWER KAMBAL & DINGALI GAON , SM/09613 | New | Material Requisition To Resource Division | RTOR000090/2022-2023 | 1378/NKWSMD | 22/09/2022 | 0 | Resource Division | 0.54 | 0.00 | 0 | 0 | ||
| Total | 107.88 | 81.50 | 75.55 | ||||||||||||||