| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 5 | 295.7 | 212.78 | 71.96 | ||||||||||||||
| 1 | KALIMPONG | Kalimpong-II | Neorakhola W/S & Mtc.Div. | PWS SCHEME FROM 9TH MILE JHORA TO 18TH MILE , SM/09603 | New | The Supply, Installation, commissioning & Monitoring of "Non-Electrical Continuous Chlorinator" approved by Government of India & recommended by National Jal Jeevan Mission (NJJM) supplied through Piped Water Supply Schemes (PWSS) maintained by the Public Health Engineering Department (PHED) Government of West Bengal for a minimum period of 03 (Three) months in the District of Kalimpong under different Schemes (As per Schedule) Tentative number of units:6 Unit (Each Unit containing 2 no of Device) | Assistant Engineer II | Junior Engineer II | ORD/000046/2023-2024 | 259/NKWSMD | 15/05/2023 | 92 | SUNANDA ENVIROMENTAL INTERNATIONAL PVT. LTD. | 31.66 | 0.00 | 0 | 0 |
| 2 | KALIMPONG | Kalimpong-II | Neorakhola W/S & Mtc.Div. | PWS SCHEME FROM 9TH MILE JHORA TO 18TH MILE , SM/09603 | New | Material Requisition To Resource Division | RTOR000037/2021-2022 | 839/NKWSMD | 21/03/2022 | 0 | Resource Division | 0.66 | 0.00 | 0 | 0 | ||
| 3 | KALIMPONG | Kalimpong-II | Neorakhola W/S & Mtc.Div. | PWS SCHEME FROM 9TH MILE JHORA TO 18TH MILE , SM/09603 | New | Material Requisition To Resource Division | RTOR000089/2022-2023 | 1374/NKWSMD | 22/09/2022 | 0 | Resource Division | 0.66 | 0.00 | 0 | 0 | ||
| 4 | KALIMPONG | Kalimpong-II | Neorakhola W/S & Mtc.Div. | PWS SCHEME FROM 9TH MILE JHORA TO 18TH MILE , SM/09603 | New | FOREST PAYMENT | BILL/00961/2023-2024 | BP-2023-24-645 | 28/03/2024 | 0 | WEST BENGAL PARIVESH CAMPA | 11.59 | 0.00 | 0 | 0 | ||
| 5 | KALIMPONG | Kalimpong-II | Neorakhola W/S & Mtc.Div. | PWS SCHEME FROM 9TH MILE JHORA TO 18TH MILE , SM/09603 | New | P.W.S SCHEME FROM 9th MILE JHORA TO 18th MILE AND ITS ADJOINING AREA UNDERPAIYONG G.P. BLOCK-II, KALIMPONG UNDER JAL JEEVAN MISSION AND JAL SWAPNO PROGRAMME, DISTRICT- KALIMPONG. | Assistant Engineer I | Junior Engineer III | ORD/000111/2021-2022 | 629/NKWSMD | 21/02/2022 | 750 | SUNIL BAJLA | 251.13 | 212.78 | 84.73 | 100 |
| Total | 295.71 | 212.78 | 71.96 | ||||||||||||||