| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 5 | 819.21 | 435.29 | 53.14 | ||||||||||||||
| 1 | KALIMPONG | Kalimpong-I | Neorakhola W/S & Mtc.Div. | DETAILED PROJECT REPORT FOR PROPOSED GRAVETY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR PEMLINGKHASMAHAL, BLOCK : KALIMPONG - I, DISTRICT : Kalimpong , SM/14192 | New | Material Requisition To Resource Division | RTOR000254/2022-2023 | 2747/NKWSMD | 06/03/2023 | 0 | Resource Division | 4.25 | 0.00 | 0 | 0 | ||
| 2 | KALIMPONG | Kalimpong-I | Neorakhola W/S & Mtc.Div. | DETAILED PROJECT REPORT FOR PROPOSED GRAVETY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR PEMLINGKHASMAHAL, BLOCK : KALIMPONG - I, DISTRICT : Kalimpong , SM/14192 | New | Demand raised for forest clearance of JJM scheme under Kalimpong Division PHED | BILL/00456/2023-2024 | BP-2023-24-289 | 01/11/2023 | 0 | WEST BENGAL PARIVESH CAMPA | 16.72 | 0.00 | 0 | 0 | ||
| 3 | KALIMPONG | Kalimpong-I | Neorakhola W/S & Mtc.Div. | DETAILED PROJECT REPORT FOR PROPOSED GRAVETY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR PEMLINGKHASMAHAL, BLOCK : KALIMPONG - I, DISTRICT : Kalimpong , SM/14192 | New | Cost of Construction of 20 nos. of boundary pillers @ Rs. 3866 (Total no of executed is 5 nos including source tanks. Therefore one tank to be needs 4 nos. of pillers in four corners. | BILL/00594/2024-2025 | 20/11/2024 | 0 | WBSFDA | 0.77 | 0.00 | 0 | 0 | |||
| 4 | KALIMPONG | Kalimpong-I | Neorakhola W/S & Mtc.Div. | DETAILED PROJECT REPORT FOR PROPOSED GRAVETY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR PEMLINGKHASMAHAL, BLOCK : KALIMPONG - I, DISTRICT : Kalimpong , SM/14192 | New | FOREST PAYMENT | BILL/00961/2023-2024 | BP-2023-24-645 | 28/03/2024 | 0 | WEST BENGAL PARIVESH CAMPA | 11.59 | 0.00 | 0 | 0 | ||
| 5 | KALIMPONG | Kalimpong-I | Neorakhola W/S & Mtc.Div. | DETAILED PROJECT REPORT FOR PROPOSED GRAVETY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR PEMLINGKHASMAHAL, BLOCK : KALIMPONG - I, DISTRICT : Kalimpong , SM/14192 | New | PROPOSED GRAVITY BASED & PUMPING BASED PIPED WATER SUPPLY SCHEME FOR PEMLING KHASMAHAL UNDER BLOCK: KALIMPONG - I, DISTRICT:KALIMPONG | ORD/000338/2022-2023 | 2735/NKWSMD | 03/03/2023 | 730 | ALLIED INSTRUMENTS | 785.88 | 435.29 | 55.39 | 100 | ||
| Total | 819.22 | 435.29 | 53.14 | ||||||||||||||