Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 165.02 86.71 52.55  
1 KALIMPONG Kalimpong -I Neorakhola W/S & Mtc.Div. Chunabhatti Bazar D.I.F & Lish Forest Piped Water Supply Scheme. , SM/10729 New new connection BILL/00021/2022-2023 BP-2022-23-239 21/12/2022 WBSEDCL 0.26 0.00 0 0
2 KALIMPONG Kalimpong -I Neorakhola W/S & Mtc.Div. Chunabhatti Bazar D.I.F & Lish Forest Piped Water Supply Scheme. , SM/10729 New new connection BILL/00022/2022-2023 BP-2022-23-238 21/12/2022 WBSEDCL 0.26 0.00 0 0
3 KALIMPONG Kalimpong -I Neorakhola W/S & Mtc.Div. Chunabhatti Bazar D.I.F & Lish Forest Piped Water Supply Scheme. , SM/10729 New Material Requisition To Resource Division RTOR000099/2022-2023 1552/NKWSMD 19/10/2022 Resource Division 0.89 0.00 0 0
4 KALIMPONG Kalimpong -I Neorakhola W/S & Mtc.Div. Chunabhatti Bazar D.I.F & Lish Forest Piped Water Supply Scheme. , SM/10729 New Material Requisition To Resource Division RTOR000098/2022-2023 1527/NKWSMD 18/10/2022 Resource Division 1.21 0.00 0 0
5 KALIMPONG Kalimpong -I Neorakhola W/S & Mtc.Div. Chunabhatti Bazar D.I.F & Lish Forest Piped Water Supply Scheme. , SM/10729 New Demand raised for forest clearance of JJM scheme under Kalimpong Division PHED BILL/00496/2023-2024 BP-2023-24-298 07/11/2023 WEST BENGAL PARIVESH CAMPA 6.07 0.00 0 0
6 KALIMPONG Kalimpong -I Neorakhola W/S & Mtc.Div. Chunabhatti Bazar D.I.F & Lish Forest Piped Water Supply Scheme. , SM/10729 New Supplementary Piped Water Supply Scheme for Chunabatti Bazar D.I.F & Lish Forest under Kalimpong-I Block District Kalimpong under Neorakhola Water Supply & Maintenance Division, Public Health Engineering Directorate. ORD/000279/2023-2024 156/NKWSMD 30/01/2024 60 SRINIWAS AGARWAL 20.60 0.00 0 0
7 KALIMPONG Kalimpong -I Neorakhola W/S & Mtc.Div. Chunabhatti Bazar D.I.F & Lish Forest Piped Water Supply Scheme. , SM/10729 New FOREST PAYMENT BILL/00961/2023-2024 BP-2023-24-645 28/03/2024 WEST BENGAL PARIVESH CAMPA 11.59 0.00 0 0
8 KALIMPONG Kalimpong -I Neorakhola W/S & Mtc.Div. Chunabhatti Bazar D.I.F & Lish Forest Piped Water Supply Scheme. , SM/10729 New FOREST PAYMENT BILL/00961/2023-2024 BP-2023-24-645 28/03/2024 WEST BENGAL PARIVESH CAMPA 11.59 0.00 0 0
9 KALIMPONG Kalimpong -I Neorakhola W/S & Mtc.Div. Chunabhatti Bazar D.I.F & Lish Forest Piped Water Supply Scheme. , SM/10729 New PIPED WATER SUPPLY SCHEME FOR CHUNABHATTI BAZAR D.I.F & LISH FOREST UNDER KALIMPONG-I BLOCK, DISTRICT KALIMPONG, UNDER NEORAKHOLA WATER SUPPLY & MAINTENANCE DIVISION, PHE DTE. Assistant Engineer II Junior Engineer I ORD/000074/2022-2023 590/NKWSMD 26/05/2022 180 SRINIWAS AGARWAL 112.55 86.71 77.04 80
Total 165.03 86.71 52.54