Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
11 688.75 349.72 50.78  
1 ALIPURDUAR Kumargram Alipurduar Division Chengmari Piped Water Supply Scheme , SM/18152 New Supply of CIDF & CISS Pipes and specials for Paschim Chegmari WSS Under Alipurduar Division P.H.E Dte. Alipurduar Sadar Sub Division Alipurduar Sub Division ORD/000233/2023-2024 1597/ALD 25/08/2023 30 M/S SSB CONSTRUCTION CO. 6.77 0.00 0 0
2 ALIPURDUAR Kumargram Alipurduar Division Chengmari Piped Water Supply Scheme , SM/18152 New Material Requisition To Resource Division RTOR000052/2023-2024 2698/ALD 12/12/2023 0 Resource Division 21.43 0.00 0 0
3 ALIPURDUAR Kumargram Alipurduar Division Chengmari Piped Water Supply Scheme , SM/18152 New Laying of distribution system with HDPE/DI pipeline, Providing FHTC and others allied works for Chengmari PWSS Under Alipurduar Division PHE DTE. Alipurduar Sadar Sub Division Alipurduar Sub Division ORD/000015/2023-2024 233/ALD 04/05/2023 270 HARIDAS GHOSH 248.85 205.79 82.7 65
4 ALIPURDUAR Kumargram Alipurduar Division Chengmari Piped Water Supply Scheme , SM/18152 New Material Requisition To Resource Division RTOR000100/2023-2024 214/ALD 10/01/2024 0 Resource Division 10.47 0.00 0 0
5 ALIPURDUAR Kumargram Alipurduar Division Chengmari Piped Water Supply Scheme , SM/18152 New Material Requisition To Resource Division RTOR000014/2024-2025 3948/ALD 26/11/2024 0 Resource Division 10.47 0.00 0 0
6 ALIPURDUAR Kumargram Alipurduar Division Chengmari Piped Water Supply Scheme , SM/18152 New Material Requisition To Resource Division RTOR000050/2024-2025 4270/ALD 13/12/2024 0 Resource Division 22.34 0.00 0 0
7 ALIPURDUAR Kumargram Northern Mechanical Division II Chengmari Piped Water Supply Scheme , SM/18152 New New Service Connection Charges for Chegmari PWSS PH NO-1 BILL/00735/2024-2025 BP-193/24-25 09/07/2024 0 WBSEDCL 3.31 0.00 0 0
8 ALIPURDUAR Kumargram Northern Mechanical Division II Chengmari Piped Water Supply Scheme , SM/18152 New New Service Connection for Chengmari PWSS P/H NO-2 BILL/00825/2024-2025 BP-272/24-25 12/08/2024 0 WBSEDCL 0.76 0.00 0 0
9 ALIPURDUAR Kumargram Alipurduar Division Chengmari Piped Water Supply Scheme , SM/18152 New Constructions of pump house and Tube well Boring by ODEX-165 Method of drilling at HW site and 2nd site, Laying of distribution system with HDPE pipeline including rising main and delivery connection, Constructions of 200 Cum OHR as per Departmental Design and drawing along with the Soil investigation works, providing FHTC and others allied works for Chengmari PWSS Under Alipurduar Division PHE DTE. Alipurduar Sadar Sub Division Alipurduar Sub Division ORD/000055/2023-2024 423/ALD 24/05/2023 678 HARIDAS GHOSH 240.70 143.93 59.8 85
10 ALIPURDUAR Kumargram Alipurduar Division Chengmari Piped Water Supply Scheme , SM/18152 New Supplying and Laying of Water supply line (using HDD/micro tunneling machine) for supply of drinking water in different areas of Alipurduar district under Alipurduar Division PHE Dte. Birpara A.E,HQ-A.E RWS Falakata Block,RWS Kumargram Block ORD/000464/2024-2025 5287/ALD 07/03/2025 240 APEX ENGINEERING 74.36 0.00 0 65
11 ALIPURDUAR Kumargram Alipurduar Division Chengmari Piped Water Supply Scheme , SM/18152 New Laying of new HDPE pipeline for interconnection in the distributation system and bridge/culvert crossing and other allied works in connection with Chengmari PWSS under Alipurduar Division, PHE Dte. Alipurduar Sadar Sub Division Alipurduar Sub Division ORD/000078/2025-2026 976/ALD 12/06/2025 90 HARI CONSTRUCTION 49.29 0.00 0 0
Total 688.73 349.72 50.78