Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 646.14 245.87 38.05  
1 ALIPURDUAR Falakata Northern Mechanical Division II MALSAGAON PIPED WATER SUPPLY SCHEME , SM/16818 New Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for Rejuvenation of MALSAGAON water supply scheme, TW no I AND II under JJM under NMD-II, PHE Dte. APD. Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Northern Mechanical Division-II,PHE ORD/000963/2023-2024 2572/NMD-II 22/08/2023 30 M/S ANJALI ENTERPRISE 22.82 0.00 0 0
2 ALIPURDUAR Falakata Alipurduar Division MALSAGAON PIPED WATER SUPPLY SCHEME , SM/16818 New Material Requisition To Resource Division RTOR000066/2023-2024 2776/ALD 18/12/2023 Resource Division 9.12 0.00 0 0
3 ALIPURDUAR Falakata Alipurduar Division MALSAGAON PIPED WATER SUPPLY SCHEME , SM/16818 New Rising Main, Laying of DI (K7), gap filling of HDPE pipe, construction of sluice valve chamber for washout purpose in the command area of Malsagaon PWSS under Alipurduar Division, PHE Dte. Birpara A.E RWS Falakata Block ORD/000341/2023-2024 2542/ALD 28/11/2023 90 BHAGWATI BHUJEL 76.02 36.96 48.62 95
4 ALIPURDUAR Falakata Northern Mechanical Division II MALSAGAON PIPED WATER SUPPLY SCHEME , SM/16818 New NEW SERVICE CONNECTION CHARGES FOR MALSAGAON PWSS TW NO-II IN THE DIST OF ALIPURDUAR. BILL/00632/2024-2025 BP-174/24-25 03/07/2024 WBSEDCL 0.50 0.00 0 null
5 ALIPURDUAR Falakata Northern Mechanical Division II MALSAGAON PIPED WATER SUPPLY SCHEME , SM/16818 New NEW SERVICE CONNECTION CHARGES FOR MALSAGAON PWSS TW NO-II IN THE DIST OF ALIPURDUAR. BILL/00632/2024-2025 BP-174/24-25 03/07/2024 WBSEDCL 0.50 0.00 0 null
6 ALIPURDUAR Falakata Northern Mechanical Division II MALSAGAON PIPED WATER SUPPLY SCHEME , SM/16818 New New Service connection charges under Malsagaon pwss TW no-I in the dist of Alipurduar. BILL/00662/2024-2025 BP-175/24-25 03/07/2024 WBSEDCL 9.94 0.00 0 null
7 ALIPURDUAR Falakata Northern Mechanical Division II MALSAGAON PIPED WATER SUPPLY SCHEME , SM/16818 New New Service connection charges under Malsagaon pwss TW no-I in the dist of Alipurduar. BILL/00662/2024-2025 BP-175/24-25 03/07/2024 WBSEDCL 9.94 0.00 0 null
8 ALIPURDUAR Falakata Alipurduar Division MALSAGAON PIPED WATER SUPPLY SCHEME , SM/16818 New Construction of tubewells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site, soil investigation at HW site, constructions of 350 Cum OHR at HW, construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Malsagaon PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. Birpara A.E Alipurduar Sub Division,RWS Falakata Block ORD/000252/2023-2024 1874/ALD 07/09/2023 180 DILIP MAHATO 517.30 208.91 40.38 81
Total 646.14 245.87 38.05