1 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Material Requisition To Resource Division |
|
|
RTOR000005/2023-2024 |
186/ALD |
28/04/2023 |
0 |
Resource Division |
246.11 |
0.00 |
0 |
0 |
2 |
ALIPURDUAR |
Kumargram |
Northern Mechanical Division II |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
QUOTATION FOR NEW SERVICE CONNECTION AT PURBA NARTHALI PWSS PH NO-I |
|
|
BILL/00035/2023-2024 |
BP-2023-24-49 |
12/05/2023 |
0 |
WBSEDCL |
1.21 |
0.00 |
0 |
0 |
3 |
ALIPURDUAR |
Kumargram |
Northern Mechanical Division II |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
QUOTATION FOR NEW SERVICE CONNECTION AT PURBA NARTHALI PWSS PH NO-II |
|
|
BILL/00036/2023-2024 |
BP-2023-24-48 |
12/05/2023 |
0 |
WBSEDCL |
1.21 |
0.00 |
0 |
0 |
4 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Material Requisition To Resource Division |
|
|
RTOR000102/2023-2024 |
26/ALD |
10/01/2024 |
0 |
Resource Division |
10.95 |
0.00 |
0 |
0 |
5 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Supply of DI specials and CI Jeffy coupling for Purba Narathali Water Supply Scheme(SM/16537) of Kumargram Block under Alipurduar Division P.H.E. Dte. |
Alipurduar Sadar Sub Division |
Birpara Sub Division |
ORD/000514/2023-2024 |
833/ALD |
14/03/2024 |
30 |
DILIP MAHATO |
13.51 |
0.00 |
0 |
0 |
6 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Land Development, repairing of Pump house, construction of Pathway and protection work of 3rd TW site of Narathali PWSS under Alipurduar Divn, PHE Dte. |
Alipurduar Sadar Sub Division |
Alipurduar Sub Division |
ORD/000334/2023-2024 |
2520/ALD |
24/11/2023 |
60 |
SREE MAA CONSTRUCTION |
6.99 |
0.00 |
0 |
100 |
7 |
ALIPURDUAR |
Kumargram |
Northern Mechanical Division II |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
ADDITIONAL QUOTATION FOR PURBA NARARTHALI PH NO-I |
|
|
BILL/00043/2024-2025 |
BP-04/24-25 |
08/04/2024 |
0 |
WBSEDCL |
2.27 |
0.00 |
0 |
0 |
8 |
ALIPURDUAR |
Kumargram |
Northern Mechanical Division II |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
ADDITIONAL QUOTATION FOR PURBA NARARTHALI PH NO-2 |
|
|
BILL/00045/2024-2025 |
BP-05/24-25 |
08/04/2024 |
0 |
WBSEDCL |
12.74 |
0.00 |
0 |
0 |
9 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Repairing of HW site boundary wall (40M), construction of pathway, surface drain, chatal and other misc works related to Narathali PWSS under Alipurduar Division, PHE Dte. |
Alipurduar Sadar Sub Division |
Alipurduar Sub Division |
ORD/000338/2023-2024 |
2524/ALD |
24/11/2023 |
60 |
TAPAN CHANDA |
5.33 |
0.00 |
0 |
100 |
10 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Constructions of pump house & Tube well Boring by ODEX-165 Method of drilling at HW site & 2nd site , laying of distribution system with UPVC pipeline including rising main & delivery connection, Constructions of 250 Cum OHR as per Departmental Desig |
Alipurduar Sadar Sub Division |
Alipurduar Sub Division |
ORD/000550/2022-2023 |
3573ALD |
27/03/2023 |
720 |
MADHAB SAHA |
373.15 |
232.50 |
62.31 |
80 |
11 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Laying of rising main line with HDPE PN10, horizontal boring by HDD method , bridge and culvert crossing, construction of pathway, surface drain and chatal, installation of paver block, land development along with the other allied works at PURBA NARATHALI |
Alipurduar Sadar Sub Division |
Alipurduar Sub Division |
ORD/000371/2023-2024 |
87/ALD |
10/01/2024 |
90 |
MADHAB SAHA |
34.86 |
0.00 |
0 |
45 |
12 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Laying of new UPVC/DI pipeline for interconnection in the distribution system, fixing of FHTC by means of PCC Concrete Block and others allied works in connection with the Purba Narathali (SM/16537) PWSS under Alipurduar Division, PHE Dte. |
Alipurduar Sadar Sub Division |
Alipurduar Sub Division |
ORD/000348/2024-2025 |
3418/ALD |
26/09/2024 |
60 |
MADHAB SAHA |
57.80 |
0.00 |
0 |
0 |
13 |
ALIPURDUAR |
Kumargram |
Northern Mechanical Division II |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Purba Narthali Water Supply Scheme TW No.- I and,II under NMD-II,PHE.Dte,APD. |
Assistant Engineer,Alipurduar Mechanical Sub-Division,P |
Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, |
ORD/001046/2023-2024 |
2693/NMD-II |
14/09/2023 |
684 |
P K ENGINEERING |
21.75 |
0.00 |
0 |
70 |
14 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Supply of CIDF Specials and Jeffy Coupling for Purba Narathali (SM/16537) WSS under Alipurduar Division, PHE Dte. |
Alipurduar Sadar Sub Division |
Birpara Sub Division |
ORD/000400/2024-2025 |
4266/ALD |
13/12/2024 |
30 |
HITANGSHU CHOUDHURY |
19.67 |
0.00 |
0 |
0 |
15 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Material Requisition To Resource Division |
|
|
RTOR000047/2024-2025 |
4267/ALD |
13/12/2024 |
0 |
Resource Division |
13.19 |
0.00 |
0 |
0 |
16 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
RESTORATION OF PIPELINE DAMAGED DUE TO CONSTRUCTION ACTIVITY WBSRDA |
|
|
BILL/00501/2024-2025 |
321/24-25/PFMS |
14/11/2024 |
0 |
EXECUTIVE ENGINEER WBSRDA |
64.01 |
0.00 |
0 |
0 |
17 |
ALIPURDUAR |
Kumargram |
Northern Mechanical Division II |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Solarization of grid connected pumping installation at Different PWSS at Kumargram Block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte. |
Assistant Engineer,Alipurduar Mechanical Sub-Division,P |
|
ORD/001206/2024-2025 |
820/NMD-II |
06/03/2025 |
30 |
WATER TECH |
29.68 |
0.00 |
0 |
0 |
18 |
ALIPURDUAR |
Kumargram |
Alipurduar Division |
PURBBA NARATHALI PIPED WATER SUPPLY SCHEME. , SM/16537 |
New |
Supplying and Laying of Water supply line (using HDD/micro tunneling machine) for supply of drinking water in different areas of Alipurduar district under Alipurduar Division PHE Dte. |
HQ-A.E |
RWS Kumargram Block |
ORD/000464/2024-2025 |
5287/ALD |
07/03/2025 |
120 |
APEX ENGINEERING |
74.36 |
0.00 |
0 |
0 |