Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Showing 1 to 5 of 5 entries
Sl No.District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrustedName of JE entrustedSystem Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 83.1800 
Sl No.
District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted
Name of JE entrusted
System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5
83.18
0
0
 
Total
83.18
0.00
0
 
1 ALIPURDUAR Kalchini Alipurduar Division BUXA PIPE WATER SUPPLY SCHEME , SM/16507 New Material Requisition To Resource Division RTOR000022/2023-2024 1260/ALD 10/08/2023 Resource Division 2.17 0.00 0 0
2 ALIPURDUAR Kalchini Northern Mechanical Division II BUXA PIPE WATER SUPPLY SCHEME , SM/16507 New Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for BUXA PWSS,TW No.-I and II under NMDII, PHE.Dte,Alipurduar. Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, ORD/000947/2023-2024 2532/NMD-II 16/08/2023 30 MUSTAFI CONCERN 25.54 0.00 0 0
3 ALIPURDUAR Kalchini Alipurduar Division BUXA PIPE WATER SUPPLY SCHEME , SM/16507 New Material Requisition To Resource Division RTOR000078/2023-2024 102/ALD 10/01/2024 Resource Division 16.34 0.00 0 0
4 ALIPURDUAR Kalchini Alipurduar Division BUXA PIPE WATER SUPPLY SCHEME , SM/16507 New Construction of RCC clear water Reservoir (CWR) of capacity 100 cum, laying distribution system and providing FHTC at Buxa PWSS under Alipurduar Division, PHE Dte. HQ-A.E Alipurduar Sub Division ORD/000563/2022-2023 3506/ALD 23/03/2023 180 ASHOK SAPKOTA 30.80 0.00 0 100
5 ALIPURDUAR Kalchini Alipurduar Division BUXA PIPE WATER SUPPLY SCHEME , SM/16507 New LAYING OF 25 MM DIA PP-R PIPES FROM TASHIGAON RIVER TO LEPCHAKHA AND LEPCHAKHA TO DUMBA AND OTHER ALLIED WORKS UNDER JJM PROGRAMME UNDER ALIPURDUAR DIVISION, PHE DTE. HQ-A.E Alipurduar Sub Division ORD/000439/2024-2025 5042/ALD 17/02/2025 30 S.D. PROJECT 8.33 0.00 0 0
Total 83.180.000 