| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 7 | 961.3 | 32.59 | 3.39 | ||||||||||||||
| 1 | ALIPURDUAR | Kalchini | Alipurduar Division | UTTAR BARAJHAR FOREST PIPE WATER SUPPLY SCHEME , SM/15914 | New | Providing FHTC from existing distribution system as per specification for Uttar Barajhar PWSS PWSS under Alipurduar Division, PHE Dte. | HQ-A.E | RWS Kalchini Block | ORD/000270/2023-2024 | 1887/ALD | 07/09/2023 | 30 | TAPASH DAS | 4.24 | 0.00 | 0 | 0 |
| 2 | ALIPURDUAR | Kalchini | Northern Mechanical Division II | UTTAR BARAJHAR FOREST PIPE WATER SUPPLY SCHEME , SM/15914 | New | Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Uttar Barajhar FOREST Water Supply Scheme TW No.- I AND II under NMD-II,PHE.Dte,APD. | ORD/001095/2023-2024 | 2809/NMD-II | 09/10/2023 | 30 | SUBODH KUMAR BANIK | 19.86 | 0.00 | 0 | 0 | ||
| 3 | ALIPURDUAR | Kalchini | Alipurduar Division | UTTAR BARAJHAR FOREST PIPE WATER SUPPLY SCHEME , SM/15914 | New | Material Requisition To Resource Division | RTOR000034/2022-2023 | 3014/ALD, | 07/02/2023 | 0 | Resource Division | 10.87 | 0.00 | 0 | 0 | ||
| 4 | ALIPURDUAR | Kalchini | Alipurduar Division | UTTAR BARAJHAR FOREST PIPE WATER SUPPLY SCHEME , SM/15914 | New | Tube well Boring by ODEX-165 Method of drilling at HW, FIRST TUBE WELL site including laying distribution system with new UPVC pipeline , Constructions of 100 Cum OHR as per Departmental Design & drawing including soil investigation works, TWO nos. pump house & boundary wall, providing FHTC and others allied works for UTTAR BARAJHAR FOREST PWSS Under Alipurduar Division PHE DTE. (2nd call) | HQ-A.E | RWS Kalchini Block | ORD/000011/2023-2024 | 134/ALD | 24/04/2023 | 180 | TAPASH DAS | 193.20 | 32.59 | 16.87 | 15 |
| 5 | ALIPURDUAR | Kalchini | Alipurduar Division | UTTAR BARAJHAR FOREST PIPE WATER SUPPLY SCHEME , SM/15914 | New | Material Requisition To Resource Division | RTOR000079/2023-2024 | 103/ALD | 10/01/2024 | 0 | Resource Division | 3.49 | 0.00 | 0 | 0 | ||
| 6 | ALIPURDUAR | Kalchini | Alipurduar Division | UTTAR BARAJHAR FOREST PIPE WATER SUPPLY SCHEME , SM/15914 | New | Material Requisition To Resource Division | RTOR000025/2024-2025 | 3983/ALD | 27/11/2024 | 0 | Resource Division | 3.49 | 0.00 | 0 | 0 | ||
| 7 | ALIPURDUAR | Kalchini | Northern Mechanical Division II | UTTAR BARAJHAR FOREST PIPE WATER SUPPLY SCHEME , SM/15914 | New | Implementation of Affordable IoT-Enabled Water Service Delivery Measurement and Monitoring Sensing System for Rural Deployment in the Proposed Villages Under Different Water Supply Schemes at Diferrent Block of Alipurduar District in West Bengal | Assistant Engineer,Alipurduar Mechanical Sub-Division,P | Junior Engineer 1, Cooch-Behar Mechanical Sub-Division,,Junior Engineer 1, Northern Mechanical Division-II,PHE ,Junior Engineer 2,Alipurduar Mechanical sub-division,PH | ORD/000062/2025-2026 | 1155/NMD-II | 19/05/2025 | 180 | WEBEL TECHNOLOGY LIMITED | 726.15 | 0.00 | 0 | 0 |
| Total | 961.31 | 32.59 | 3.39 | ||||||||||||||