Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 117.39 40.25 34.29  
1 ALIPURDUAR Madarihat Alipurduar Division GAROCHIRA BANDAPANI PIPED WATER SUPPLY SCHEME , SM/14216 New Construction of Tubewell by ODEX-165 method of drilling at HW site, construction of pump house and boundary wall at H/W site, laying of distribution line and providing FHTC as per Departmental Design & drawing for Garochera Bandapani PWSS Under Birpara Sub-division, Alipurduar Division PHE DTE. Birpara A.E Birpara Sub Division ORD/000451/2022-2023 2922/ALD 19/01/2023 120 RATAN DUTTA 73.26 35.62 48.62 62
2 ALIPURDUAR Madarihat Northern Mechanical Division II GAROCHIRA BANDAPANI PIPED WATER SUPPLY SCHEME , SM/14216 New Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Garochira Bandapani Water Supply Scheme TW No.-I under NMD-II,PHE.Dte,Apd. Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, ORD/000400/2023-2024 1674/NMD-II 17/07/2023 30 PRAGATI CONSTRUCTION COMPANY 9.38 4.63 49.36 100
3 ALIPURDUAR Madarihat Alipurduar Division GAROCHIRA BANDAPANI PIPED WATER SUPPLY SCHEME , SM/14216 New Material Requisition To Resource Division RTOR000045/2023-2024 1953/ALD 12/09/2023 Resource Division 33.29 0.00 0 0
4 ALIPURDUAR Madarihat Northern Mechanical Division II GAROCHIRA BANDAPANI PIPED WATER SUPPLY SCHEME , SM/14216 New QUOTATION FOR NEW SERVICE CONNECTION AT GAROCHIRA BANDAPANI TW NO-I BILL/00064/2023-2024 BP-2023-24-58 13/05/2023 WBSEDCL 1.46 0.00 0 0
Total 117.40 40.25 34.28