Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 517.7 323.98 62.58  
1 ALIPURDUAR Alipurduar - II Alipurduar Division PURBA KHALISHAMARI PIPED WATER SUPPLY SCHEME. , SM/13243 New Material Requisition To Resource Division RTOR000036/2022-2023 3044/ALD 08/02/2023 Resource Division 21.01 0.00 0 0
2 ALIPURDUAR Alipurduar - II Northern Mechanical Division II PURBA KHALISHAMARI PIPED WATER SUPPLY SCHEME. , SM/13243 New NEW SERVICE CONNECTIO CHARGE FOR PURBA KHALISHAMARI W/S/S P/H NO.1 BILL/00592/2023-2024 BP-2023-24-181 15/06/2023 WBSEDCL 1.41 0.00 0 0
3 ALIPURDUAR Alipurduar - II Northern Mechanical Division II PURBA KHALISHAMARI PIPED WATER SUPPLY SCHEME. , SM/13243 New NEW SERVICE CONNECTION CHARGE FOR PURBA KHALISHAMARI W/S/S P/H NO.2 BILL/00593/2023-2024 BP-2023-24-182 15/06/2023 WBSEDCL 1.41 0.00 0 0
4 ALIPURDUAR Alipurduar - II Alipurduar Division PURBA KHALISHAMARI PIPED WATER SUPPLY SCHEME. , SM/13243 New Supply of CIDF & CISS Pipes and specials for Purba Khalshamari WSS Under Alipurduar Division P.H.E Dte. Alipurduar Sadar Sub Division Alipurduar Sub Division ORD/000229/2023-2024 1604/ALD 25/08/2023 30 HARI CONSTRUCTION 6.76 0.00 0 0
5 ALIPURDUAR Alipurduar - II Alipurduar Division PURBA KHALISHAMARI PIPED WATER SUPPLY SCHEME. , SM/13243 New Material Requisition To Resource Division RTOR000082/2023-2024 106/ALD 10/01/2024 Resource Division 11.82 0.00 0 0
6 ALIPURDUAR Alipurduar - II Northern Mechanical Division II PURBA KHALISHAMARI PIPED WATER SUPPLY SCHEME. , SM/13243 New Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for PURBA KHALISHAMARI water supply scheme, TW no I and II under Northern Mechanical Division-II, PHE Dte.Alipurduar. Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 2,Alipurduar Mechanical sub-division,PH ORD/000793/2023-2024 2365/NMD-II 08/08/2023 30 MENAKA ENTERPRISE 21.73 10.19 46.89 100
7 ALIPURDUAR Alipurduar - II Alipurduar Division PURBA KHALISHAMARI PIPED WATER SUPPLY SCHEME. , SM/13243 New Constructions of pump house & Sinking of 250 mm x 200 mm X 150 mtr. Big dia. Tube well at HW site & 2nd site , laying of distribution system with UPVC pipeline , Constructions of 250 Cum OHR as per Departmental Design & drawing including soil test, providing FHTC and others allied works for Purba Khalisamari PWSS Under Alipurduar Division PHE DTE. Alipurduar Sadar Sub Division Alipurduar Sub Division ORD/000557/2022-2023 3577/ALD 27/03/2023 540 HARIDAS GHOSH 438.25 306.26 69.88 72
8 ALIPURDUAR Alipurduar - II Alipurduar Division PURBA KHALISHAMARI PIPED WATER SUPPLY SCHEME. , SM/13243 New Supply of CIDF/CIPE Pipes and Special & CI Jeffy Coupling for Purba Khalishamari Water Supply Scheme under Alipurduar Division P.H.E. Dte. Alipurduar Sadar Sub Division Birpara Sub Division ORD/000481/2023-2024 699/ALD 07/03/2024 30 HARI CONSTRUCTION 15.31 7.53 49.18 70
Total 517.70 323.98 62.58