| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 4 | 9.36 | 5.37 | 57.37 | ||||||||||||||
| 1 | ALIPURDUAR | Alipurduar Division | PROCUREMENT OF CHEMICALS,CRM,GLASSWARE,INSTRUMENT & EQUIPMENT WITH MISCELLANEOUS ITEMS FOR INFRASTRUCTURE DEVELOPEMENT OF BIRPARA SUB DISTRICT LABORATORY FOR NABL SET-UP UNDER ALIPURDUAR DIVISION, P.H.E. DTE., 2022 , SM/12910 | Support-WQMSP | Supply, delivery and Installation of split type Air Conditioner for PHE Office Conferrence Room (left side) under Alipurduar Division, PHE Dte. | HQ-A.E | ORD/000424/2022-2023 | 2827/ALD | 11/01/2023 | 7 | BETTER LIFE | 0.64 | 0.64 | 100 | 100 | ||
| 2 | ALIPURDUAR | Alipurduar Division | PROCUREMENT OF CHEMICALS,CRM,GLASSWARE,INSTRUMENT & EQUIPMENT WITH MISCELLANEOUS ITEMS FOR INFRASTRUCTURE DEVELOPEMENT OF BIRPARA SUB DISTRICT LABORATORY FOR NABL SET-UP UNDER ALIPURDUAR DIVISION, P.H.E. DTE., 2022 , SM/12910 | Support-WQMSP | Procurement of chemical and glasswares for all laboratories under Alipurduar Division, PHE Dte. | Alipurduar RWS | ORD/000426/2022-2023 | 2829/ALD | 11/01/2023 | 15 | DULAL MAJUMDER | 0.49 | 0.49 | 100 | 100 | ||
| 3 | ALIPURDUAR | Alipurduar Division | PROCUREMENT OF CHEMICALS,CRM,GLASSWARE,INSTRUMENT & EQUIPMENT WITH MISCELLANEOUS ITEMS FOR INFRASTRUCTURE DEVELOPEMENT OF BIRPARA SUB DISTRICT LABORATORY FOR NABL SET-UP UNDER ALIPURDUAR DIVISION, P.H.E. DTE., 2022 , SM/12910 | Support-WQMSP | Calibration of laboratory instrument/equipment related to NABL Recognition of Samuktala Sub District Laboratory and Birpara Sub District Laboratory as per ISO/IEC 17025- 2017 and procurement of Chemicals/Reagents/Water sample testing equipment/Kits for 03 No's Laboratories under Alipurduar Division, PHE. Dte. | Alipurduar RWS | JUNIOR ENGINEER | ORD/000383/2024-2025 | 3777/ALD | 13/11/2024 | 60 | BHARATI CHEMICAL AND SCIENTIFIC WORKS | 8.12 | 4.24 | 52.22 | 20 | |
| 4 | ALIPURDUAR | Alipurduar Division | PROCUREMENT OF CHEMICALS,CRM,GLASSWARE,INSTRUMENT & EQUIPMENT WITH MISCELLANEOUS ITEMS FOR INFRASTRUCTURE DEVELOPEMENT OF BIRPARA SUB DISTRICT LABORATORY FOR NABL SET-UP UNDER ALIPURDUAR DIVISION, P.H.E. DTE., 2022 , SM/12910 | Support-WQMSP | Procurement of necessary Chemical for Regular water sample testing purpose of all Laboratories Under Alipurduar Division PHE DTE. | Alipurduar RWS | JUNIOR ENGINEER | ORD/000136/2025-2026 | 1573/ALD | 31/07/2025 | 30 | CHANDAN DAS | 0.11 | 0.00 | 0 | 0 | |
| Total | 9.36 | 5.37 | 57.38 | ||||||||||||||