Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
11 396.17 252.2 63.66  
1 ALIPURDUAR Kumargram Alipurduar Division KARTIKA TEA GARDEN AREA PIPED WAATER SUPPLY SCHEME , SM/11991 New Material Requisition To Resource Division RTOR000011/2023-2024 217/ALD 03/05/2023 Resource Division 18.80 0.00 0 0
2 ALIPURDUAR Kumargram Alipurduar Division KARTIKA TEA GARDEN AREA PIPED WAATER SUPPLY SCHEME , SM/11991 New Soil investigation works for proposed overhead reservoir of KARTIKA TG PWSS under Alipurduar Division, PHE Dte. Alipurduar Sadar Sub Division Birpara Sub Division ORD/000315/2022-2023 2224/ALD 21/11/2022 30 K S GROUP 0.65 0.65 100 0
3 ALIPURDUAR Kumargram Northern Mechanical Division II KARTIKA TEA GARDEN AREA PIPED WAATER SUPPLY SCHEME , SM/11991 New Quotation for NSC at P/H No.I under Kartika TG Area W/S/S BILL/00602/2023-2024 BP-2023-24-170 15/06/2023 WBSEDCL 1.31 0.00 0 0
4 ALIPURDUAR Kumargram Northern Mechanical Division II KARTIKA TEA GARDEN AREA PIPED WAATER SUPPLY SCHEME , SM/11991 New Quotation for NSC at P/H No.II under Kartika TG Area W/S/S BILL/00603/2023-2024 BP-2023-24-171 15/06/2023 WBSEDCL 1.31 0.00 0 0
5 ALIPURDUAR Kumargram Alipurduar Division KARTIKA TEA GARDEN AREA PIPED WAATER SUPPLY SCHEME , SM/11991 New Tube well Boring by ODEX-165 method at 2nd TW Site, Cons. of Pump house and boundary wall at HW site, LDS with new HDPE pipeline (Part-B) with Rising Main and delivery line connection, providing FHTC and other allied works for Kartika Tea Garden PWSS under Alipurduar Division, PHE Dte. Alipurduar Sadar Sub Division Birpara Sub Division ORD/000330/2022-2023 2239/ALD 21/11/2022 120 TAPASH DAS 79.55 66.61 83.73 84
6 ALIPURDUAR Kumargram Alipurduar Division KARTIKA TEA GARDEN AREA PIPED WAATER SUPPLY SCHEME , SM/11991 New Tube well boring by ODEX-165 Method of drilling at HW site including distribution system with new HDPE pipeline, Construction of 200 cum OHR as per Departmental Design & drawing, Providing FHTC and other allied works for KARTIKA TEA GARDEN PWSS under Alipurduar Division, PHE Dte. Alipurduar Sadar Sub Division Birpara Sub Division ORD/000455/2022-2023 2976/ALD 02/02/2023 180 MAHENDRA CHHETRI 238.07 166.94 70.12 60
7 ALIPURDUAR Kumargram Alipurduar Division KARTIKA TEA GARDEN AREA PIPED WAATER SUPPLY SCHEME , SM/11991 New Material Requisition To Resource Division RTOR000110/2023-2024 134/ALD 10/01/2024 Resource Division 6.95 0.00 0 0
8 ALIPURDUAR Kumargram Northern Mechanical Division II KARTIKA TEA GARDEN AREA PIPED WAATER SUPPLY SCHEME , SM/11991 New Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Kartika TG water supply scheme, TW no I and II of under Northern Mechanical Division-II, PHE Dte.APD Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, ORD/000676/2023-2024 2085/NMD-II 26/07/2023 30 DIAMOND ELECTRICAL WORKS 18.63 8.53 45.79 90
9 ALIPURDUAR Kumargram Alipurduar Division KARTIKA TEA GARDEN AREA PIPED WAATER SUPPLY SCHEME , SM/11991 New Supply of CIDF & CISS Pipes and specials for Kartika TG WSS Under Alipurduar Division P.H.E Dte. Alipurduar Sadar Sub Division Birpara Sub Division ORD/000223/2023-2024 1594/ALD 25/08/2023 30 JUGAL CHOUDHURY 6.76 2.80 41.42 68
10 ALIPURDUAR Kumargram Alipurduar Division KARTIKA TEA GARDEN AREA PIPED WAATER SUPPLY SCHEME , SM/11991 New Supply of DI specials and CI Jeffy coupling for Kartika TG Water Supply Scheme (SM/11991) of Kumargram Block under Alipurduar Division P.H.E. Dte. Alipurduar Sadar Sub Division Birpara Sub Division ORD/000522/2023-2024 841/ALD 14/03/2024 30 MANSAROVAR CASTING 13.34 6.67 50 92
11 ALIPURDUAR Kumargram Alipurduar Division KARTIKA TEA GARDEN AREA PIPED WAATER SUPPLY SCHEME , SM/11991 New Laying distribution system with new DI line and Supply of necessary specials, construction of sluice valve chamber, Construction of pump house and boundary wall at 2nd site of Kartika TG Area PWSS under Alipurduar Division, PHE Dte. Alipurduar Sadar Sub Division Alipurduar Sub Division,Birpara Sub Division ORD/000338/2022-2023 2247/ALD 21/11/2022 120 MONORAMA ENTERPRISE 10.80 0.00 0 78
Total 396.17 252.20 63.66