Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 69.05 29.66 42.95  
1 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HANTUPARA TG WATER SUPPLY SCHEME' , SM/09901 Augmentation Quotation for new service connection at Hantapara TW No- III BILL/00040/2022-2023 BP-129/22-23 13/01/2023 WBSEDCL 1.81 0.00 0 0
2 ALIPURDUAR Alipurduar Division REJUVENATION OF HANTUPARA TG WATER SUPPLY SCHEME' , SM/09901 Augmentation Laying of HDPE pipeline for Hantapara Topline under Hatapara WSS within Alipurduar Division, PHE Dte. Birpara A.E Birpara Sub Division ORD/000429/2021-2022 2627/ALD 18/02/2022 60 DILIP MAHATO 16.19 0.00 0 69
3 ALIPURDUAR Alipurduar Division REJUVENATION OF HANTUPARA TG WATER SUPPLY SCHEME' , SM/09901 Augmentation Construction of Pump House, Boundary Wall, and Tube well Boring by ODEX-195 method of drilling including Rising main for HANTUPARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE. Birpara A.E Alipurduar Sub Division ORD/000433/2021-2022 2713/ALD 23/02/2022 90 SUBIR GHOSH 25.31 7.67 30.3 41
4 ALIPURDUAR Alipurduar Division REJUVENATION OF HANTUPARA TG WATER SUPPLY SCHEME' , SM/09901 Augmentation Laying of additional dedicated HDPE pipeline near PH No-1 village for the Hantapara WSS under Alipurduar Division, PHE Dte. Birpara A.E Alipurduar Sub Division ORD/000482/2021-2022 2904/ALD 08/03/2022 60 SUBIR GHOSH 11.78 8.03 68.17 39
5 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HANTUPARA TG WATER SUPPLY SCHEME' , SM/09901 Augmentation Supply, delivery and installation of 25 KVA servo motor operated Copper wound line voltage corrector at Hantapara T.G Water Supply Scheme TW No.-I under NMD-II,PHE.Dte,Alipurduar. Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, ORD/000847/2022-2023 610/NMD-II 20/03/2023 20 S.K ENTERPRISE 3.30 3.30 100 100
6 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF HANTUPARA TG WATER SUPPLY SCHEME' , SM/09901 Augmentation Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Hantapara T.G water supply scheme TW No. III under NMD-II, PHE Dte. Alipurduar. Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 1, Cooch-Behar Mechanical Sub-Division, ORD/000014/2022-2023 598/NMD-II 05/05/2022 30 MIHIR SARKAR 10.66 10.66 100 100
Total 69.04 29.66 42.96