Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 98.76 21.48 21.75  
1 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF BIRPARA(APD) WATER SUPPLY SCHEME , SM/09897 Augmentation Quotation for new service connection at Birpara (apd) TG P/H No-III. Application No- 4003027982 BILL/00017/2022-2023 BP-110/22-23 19/12/2022 WBSEDCL 1.34 0.00 0 0
2 ALIPURDUAR Alipurduar Division REJUVENATION OF BIRPARA(APD) WATER SUPPLY SCHEME , SM/09897 Augmentation Extension and replacement of damaged pipeline under Birpara APD PWSS at Alipurduar-I under Alipurduar Division, P.H.E. Dte. Alipurduar RWS Birpara Sub Division ORD/000077/2021-2022 883/ALD 03/09/2021 45 KAMALESH ROY 15.92 3.32 20.85 0
3 ALIPURDUAR Alipurduar Division REJUVENATION OF BIRPARA(APD) WATER SUPPLY SCHEME , SM/09897 Augmentation Laying of Distribution Line (HDPE and DI) for retrofitting of FHTC for BIRPARA WSS under Alipurduar Division, PHE Dte. Alipurduar RWS RWS Alipurduar - I Block ORD/000360/2020-2021 1754/ALD 19/02/2021 45 BILTU DAS 47.98 0.00 0 61
4 ALIPURDUAR Alipurduar Division REJUVENATION OF BIRPARA(APD) WATER SUPPLY SCHEME , SM/09897 Augmentation Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method) and Rising Main for Additional T/W of BIRPARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE Alipurduar Sadar Sub Division Birpara Sub Division ORD/000316/2021-2022 2192/ALD 11/01/2022 90 DAS CONSTRUCTION 22.03 7.86 35.68 65
5 ALIPURDUAR Northern Mechanical Division II REJUVENATION OF BIRPARA(APD) WATER SUPPLY SCHEME , SM/09897 Augmentation Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for Rejuvenation of Birpara (APD) water supply scheme, TW no III under JJM under NMD-II, PHE Dte. APD Assistant Engineer,Alipurduar Mechanical Sub-Division,P Junior Engineer 2,Alipurduar Mechanical sub-division,PH ORD/000038/2023-2024 991/NMD-II 15/05/2023 30 P K ENGINEERING 10.95 10.30 94.06 80
6 ALIPURDUAR Alipurduar Division REJUVENATION OF BIRPARA(APD) WATER SUPPLY SCHEME , SM/09897 Augmentation Extension work order for Hiring of Diesel vehicle Maxi Cab(At least 7 seater) for Executive Engineer, Alipurduar Division under Alipurduar Division, PHE Dte.( 01.04.2021 to 30.06.2021) HQ-A.E ORD/000609/2020-2021 3051/ALD 31/03/2021 90 APSARI BHOWMICK 0.54 0.00 0 100
Total 98.76 21.48 21.75