Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
17 941.46 332.21 35.29  
1 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Providing FHTC for Bharnobari / Santali TG area including supply of CI materials and other misc. works under Alipurduar Division, P.H.E. Dte. HQ-A.E RWS Kalchini Block ORD/000073/2021-2022 880/ALD 03/09/2021 60 SOUVIK ROY PALADHI 30.69 19.40 63.21 95
2 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting PROVIDNG HOUSE CONNECTION FOR BHARNOBARI TG AREA NEAR DALSINGPARA AT KALCHINI BLOCK UNDER ALIPURDUAR DIVISION, PHE DTE. HQ-A.E RWS Kalchini Block ORD/000034/2021-2022 582/ALD 15/07/2021 30 M/S BHOWMICK CONSTRUCTION 20.03 20.03 100 96
3 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Providing House connection for KALCHINI water supply scheme at KALCHINI Block under Alipuduar Division, P.H.E. Dte.(Part-3) HQ-A.E RWS Kalchini Block ORD/000327/2020-2021 1463/ALD 25/01/2021 30 HARI CONSTRUCTION 4.98 2.15 43.17 97
4 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Providing FHTC at Southern side of Hasimara Piped Water Supply Scheme Under Alipurduar Division, PHE DTE. HQ-A.E RWS Kalchini Block ORD/000466/2021-2022 2811/ALD 28/02/2022 60 MAHENDRA CHHETRI 34.74 31.27 90.01 91
5 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Extension of pipeline to Bharnabari TG area under Hasimara PWSS for providing at Kalchini Block under Alipurduar Division, P.H.E. Dte.(Part-A) HQ-A.E RWS Kalchini Block ORD/000122/2020-2021 794/ALD 01/10/2020 60 TAPASH KUMAR BHOWMICK 40.85 17.50 42.84 98
6 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Construction of Culvert at Hasimara WSS Head Work Site within Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000264/2021-2022 1597/ALD 22/11/2021 45 ALATYA CONSTRUCTION & CO. 4.92 4.54 92.28 98
7 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Laying Distribution line of UPVC and DI with providing FHTC Connection for the Salkumar Water Supply Scheme Area under Alipurduar Division, PHE Dte. Birpara A.E,HQ-A.E Birpara Sub Division,RWS Kalchini Block ORD/000197/2021-2022 1318/ALD 05/10/2021 60 TAPASH KUMAR BHOWMICK 35.38 5.13 14.5 85
8 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Extension of pipeline from Malangi TW to Bharnobari TG area (booster line) under Hasimara PWSS at Kalchini Block under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000025/2022-2023 20/ALD 01/04/2022 60 AASHIRBAD ENTERPRISE 14.64 11.92 81.42 49.5
9 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Extension of pipeline from Santali TG connection line to upper line of Madhu TG area (booster line) under Hasimara TG PWSS at Kalchini Block under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000024/2022-2023 19/ALD 01/04/2022 60 AASHIRBAD ENTERPRISE 12.61 8.47 67.17 49
10 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Supply of various materials at Alipurduar Divisional Stack Yard under Alipurduar Division, PHE Dte. Alipurduar RWS,Alipurduar Sadar Sub Division,Birpara A.E,HQ-A.E Birpara Sub Division,RWS Alipurduar - I Block,RWS Alipurduar - II Block,RWS Kalchini Block ORD/000432/2021-2022 846/ALD 26/08/2021 30 EXECUTIVE ENGINEER, RESOURCE DIVISION 502.58 0.00 0 100
11 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Providing FHTC at Northern side of Hasimara Piped Water Supply Scheme Under Alipurduar Division, PHE DTE. HQ-A.E RWS Kalchini Block ORD/000434/2021-2022 2714/ALD 23/02/2022 60 ASHIM KUMAR GHOSH 34.64 34.64 100 49
12 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Construction of valve chamber, dismantling concrete road and other misc works at Malangi TG area within Hasimara W/S/S under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000077/2022-2023 442/ALD 13/05/2022 30 MADHAB SAHA 4.90 1.74 35.51 49
13 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Supply of CIPE Special & CI Jeffy Coupling for Augmentation of Hasimara Water Supply Scheme under Alipurduar Division P.H.E. Dte. HQ-A.E RWS Kalchini Block ORD/000111/2022-2023 703/ALD 08/06/2022 30 MADHAB SAHA 4.84 4.84 100 49.5
14 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Construction of Pump House ,Boundary Wall , Tube well Boring ( ODEX-165 Method of drilling) and Rising Main for Additional T/W of HASIMARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE. HQ-A.E RWS Kalchini Block ORD/000294/2021-2022 1992/ALD 27/12/2021 90 MAHENDRA CHHETRI 42.03 42.02 99.98 49
15 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Providing House connection for BAROBISHA ZONE- III water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte. Alipurduar RWS,Alipurduar Sadar Sub Division,HQ-A.E Alipurduar Sub Division,RWS Alipurduar - I Block,RWS Alipurduar - II Block,RWS Kalchini Block ORD/000148/2020-2021 860/ALD 14/10/2020 30 AKANSHA COMMERCIAL PRIVATE LTD. 4.98 0.00 0 78.5
16 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Laying of HDPE pipeline for Malangi Tea Garden Area within Hasimara Water Supply Scheme under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000375/2021-2022 2375/ALD 31/01/2022 60 MADHAB SAHA 74.82 69.57 92.98 94
17 ALIPURDUAR Alipurduar Division FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of HASIMARA Water Supply Scheme , SM/08884 Retrofitting Laying of HDPE pipeline for New Hasimara Area within Hasimara Water Supply Scheme under Alipurduar Division, PHE Dte. HQ-A.E RWS Kalchini Block ORD/000376/2021-2022 2376/ALD 31/01/2022 60 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 73.83 58.99 79.9 99
Total 941.47 332.21 35.29