Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 96.85 33.76 34.86  
1 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Banchukamari Piped Water Supply Scheme (Phase-1) , SM/07187 Retrofitting Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Banchukamari WSS under Alipurduar Division, PHE Dte. Part-4 Alipurduar RWS RWS Alipurduar - I Block ORD/000277/2021-2022 1844/ALD 10/12/2021 30 HIMALAYAN CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 5.04 0.94 18.65 86.5
2 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Banchukamari Piped Water Supply Scheme (Phase-1) , SM/07187 Retrofitting Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Banchukamari WSS under Alipurduar Division, PHE Dte. Part-3 Alipurduar RWS RWS Alipurduar - I Block ORD/000280/2021-2022 1843/ALD 10/12/2021 30 PROJIT HALDER 5.02 0.00 0 87
3 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Banchukamari Piped Water Supply Scheme (Phase-1) , SM/07187 Retrofitting Extension and replacement of damaged pipeline and providing FHTC at surrounding area of Banchukamari PWSS. Alipurduar-I Block under Alipurduar Division, PHE Dte. Alipurduar RWS RWS Alipurduar - I Block ORD/000378/2021-2022 2378/ALD 31/01/2022 60 SHIBA ENTERPRISE 51.82 0.00 0 86.5
4 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Banchukamari Piped Water Supply Scheme (Phase-1) , SM/07187 Retrofitting Providing House connection for Banchukamari piped water supply scheme at Alipurduar -I Block under Alipuduar Division, P.H.E. Dte. Alipurduar RWS JUNIOR ENGINEER ORD/000100/2020-2021 721/ALD 22/09/2020 30 DAS CONSTRUCTION 4.99 4.99 100 0
5 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Banchukamari Piped Water Supply Scheme (Phase-1) , SM/07187 Retrofitting Providing House connection for BHOLARDABRI PWSS under Alipuduar Division, P.H.E. Dte. ORD/000371/2020-2021 1767/ALD 19/02/2021 60 HARIDAS GHOSH 10.03 10.03 100 0
6 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Banchukamari Piped Water Supply Scheme (Phase-1) , SM/07187 Retrofitting Providing House connection for BHOLARDABRI water supply scheme at ALIPURDUAR-I Block under Alipuduar Division, P.H.E. Dte.(Part-2) ORD/000321/2020-2021 1462/ALD 25/01/2021 30 HARI CONSTRUCTION 5.01 5.01 100 0
7 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Banchukamari Piped Water Supply Scheme (Phase-1) , SM/07187 Retrofitting Providing House connection for KALCHINI water supply scheme at KALCHINI Block under Alipuduar Division, P.H.E. Dte.(Part-3) HQ-A.E RWS Kalchini Block ORD/000327/2020-2021 1463/ALD 25/01/2021 30 HARI CONSTRUCTION 4.98 2.83 56.83 97
8 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Banchukamari Piped Water Supply Scheme (Phase-1) , SM/07187 Retrofitting Providing House connection for BHOLARDABRI WSS at Alipurduar-II Block under Alipurduar Division, PHE Dte. (Part-5) Alipurduar RWS Alipurduar Sub Division ORD/000400/2020-2021 1586/ALD 10/02/2021 60 HARIDAS GHOSH 4.98 4.98 100 0
9 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Banchukamari Piped Water Supply Scheme (Phase-1) , SM/07187 Retrofitting Providing House connection for BHOLARDABRI WSS at Alipurduar-II Block under Alipurduar Division, PHE Dte. (Part-4) Alipurduar RWS Alipurduar Sub Division ORD/000399/2020-2021 1585/ALD 10/02/2021 60 HARIDAS GHOSH 4.98 4.98 100 0
Total 96.87 33.77 34.86