Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
11 202.73 49.32 24.33  
1 ALIPURDUAR Alipurduar Division FHTC under Jaldhara / Jalswapna including retrofitting of existing distribution system under DALMORE RAMJHORA T.G. Piped Water Supply Scheme (Phase-1) , SM/07133 Retrofitting Fuel bill for the month of August 2021 VCH/000567/2021-2022 117/21-22/PFMS 08/09/2021 SHIVAM SERVICE STATION 0.11 0.00 0 0
2 ALIPURDUAR Alipurduar Division FHTC under Jaldhara / Jalswapna including retrofitting of existing distribution system under DALMORE RAMJHORA T.G. Piped Water Supply Scheme (Phase-1) , SM/07133 Retrofitting Fuel bill for the month of August 2021 VCH/000570/2021-2022 121/21-22/PFMS 08/09/2021 SHIVAM SERVICE STATION 0.22 0.00 0 0
3 ALIPURDUAR Alipurduar Division FHTC under Jaldhara / Jalswapna including retrofitting of existing distribution system under DALMORE RAMJHORA T.G. Piped Water Supply Scheme (Phase-1) , SM/07133 Retrofitting Laying of balance DI/MS/HDPE pipeline for the Dalmore-Ramjhora WSS under Alipurduar Division, PHE Dte. Birpara A.E Birpara Sub Division ORD/000324/2020-2021 1456/ALD 25/01/2021 45 ASHIT KUMAR SINGHA 21.28 4.28 20.11 59
4 ALIPURDUAR Alipurduar Division FHTC under Jaldhara / Jalswapna including retrofitting of existing distribution system under DALMORE RAMJHORA T.G. Piped Water Supply Scheme (Phase-1) , SM/07133 Retrofitting Retrofitting of pipeline for Ramjhora TG PWSS area at Madarihat-Birpara Block under Alipurduar Division, P.H.E. Dte. Birpara A.E Birpara Sub Division ORD/000316/2020-2021 1447/ALD 25/01/2021 45 ASHIT KUMAR SINGHA 16.96 3.58 21.11 58
5 ALIPURDUAR Alipurduar Division FHTC under Jaldhara / Jalswapna including retrofitting of existing distribution system under DALMORE RAMJHORA T.G. Piped Water Supply Scheme (Phase-1) , SM/07133 Retrofitting Laying of HDPE pipe line for Dalmore Water Supply Scheme under Alipurduar Division, PHE Dte. Birpara A.E Birpara Sub Division ORD/000524/2021-2022 2996/ALD 15/03/2022 60 MS DEYS CONSTRUCTION 8.33 5.00 60.02 57.5
6 ALIPURDUAR Alipurduar Division FHTC under Jaldhara / Jalswapna including retrofitting of existing distribution system under DALMORE RAMJHORA T.G. Piped Water Supply Scheme (Phase-1) , SM/07133 Retrofitting Construction of Pump House with Sanitary & Plumbing arrangement at 2nd Pump House Site of Dalmore-Ramjhora WSS (Ramjhora Pump House no-2) under Alipurduar Division PHE Dte. Birpara A.E Birpara Sub Division ORD/000094/2021-2022 893/ALD 03/09/2021 60 PRAMESH LAMA 4.96 4.97 100.2 59.5
7 ALIPURDUAR Alipurduar Division FHTC under Jaldhara / Jalswapna including retrofitting of existing distribution system under DALMORE RAMJHORA T.G. Piped Water Supply Scheme (Phase-1) , SM/07133 Retrofitting Retrofitting work of pipeline of Dalmore PWSS under Alipurduar Division, PHE Dte. Birpara A.E Birpara Sub Division ORD/000198/2021-2022 971/ALD 13/09/2021 30 MS DEYS CONSTRUCTION 5.04 5.04 100 59
8 ALIPURDUAR Alipurduar Division FHTC under Jaldhara / Jalswapna including retrofitting of existing distribution system under DALMORE RAMJHORA T.G. Piped Water Supply Scheme (Phase-1) , SM/07133 Retrofitting Construction of 350 cum OHR (staging height 20 m) including boundary wal land development & pathway at HWS raising main for augmentation & associate work for Dalmore TG WSS under Jalpaiguri Division PART - A ORD/000044/2017-2018 1114/JD 03/11/2017 JAL PRAVAHIKA PVT. LTD. 131.53 12.69 9.65 0
9 ALIPURDUAR Alipurduar Division FHTC under Jaldhara / Jalswapna including retrofitting of existing distribution system under DALMORE RAMJHORA T.G. Piped Water Supply Scheme (Phase-1) , SM/07133 Retrofitting Construction of Pump House with Sanitary & Plumbing arrangement at H/W Site (Old) of Dalmore Water supply scheme under Alipurduar Division. P.H.E. Dte. Birpara A.E Birpara Sub Division ORD/000062/2020-2021 538/ALD 20/08/2020 120 PRAPTI DUTTA 4.75 4.20 88.42 0
10 ALIPURDUAR Alipurduar Division FHTC under Jaldhara / Jalswapna including retrofitting of existing distribution system under DALMORE RAMJHORA T.G. Piped Water Supply Scheme (Phase-1) , SM/07133 Retrofitting Supply and delivery of materials at APD divn stack yard for Ramjhora WSS for Shifting of pipe line due to widening of PWD Road under Apd Divn PHED ORD/000454/2018-2019 585/ALD 01/10/2018 SASANKA ROY 4.59 4.59 100 0
11 ALIPURDUAR Alipurduar Division FHTC under Jaldhara / Jalswapna including retrofitting of existing distribution system under DALMORE RAMJHORA T.G. Piped Water Supply Scheme (Phase-1) , SM/07133 Retrofitting Construction of Pump House with Sanitary & Plumbing arrangement at Headwork Site of Dalmore-Ramjhora WSS (Ramjhora Pump House no-1) under Alipurduar Division PHE Dte. Birpara A.E Birpara Sub Division ORD/000095/2021-2022 894/ALD 03/09/2021 60 PRAMESH LAMA 4.96 4.97 100.2 0
Total 202.75 49.32 24.33