Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 181.89 31.59 17.37  
1 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Tapshikatha Piped Water Supply Scheme (Phase-2) , SM/07128 Retrofitting Extension and replacement of damaged pipeline including new FHTC under Dakshin Chakoakhati mouza (Sonapur area) at Alipurduar-I Block under Alipurduar Division, PHE Dte. Alipurduar RWS,HQ-A.E RWS Alipurduar - I Block,RWS Kalchini Block ORD/000079/2021-2022 877/ALD 03/09/2021 60 M/S STAR INDIA CONSTRUCTION 33.42 0.00 0 73.2
2 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Tapshikatha Piped Water Supply Scheme (Phase-2) , SM/07128 Retrofitting Extension and replacement of damaged pipeline and providing FHTC at surrounding area of North side of Pukuritola area under Tapshikatha PWSS. Alipurduar-I Block under Alipurduar Division, PHE Dte. Alipurduar RWS RWS Alipurduar - I Block ORD/000369/2021-2022 2292/ALD 24/01/2022 60 DEBAJYOTI SUTRADHAR 26.52 24.90 93.89 77.5
3 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Tapshikatha Piped Water Supply Scheme (Phase-2) , SM/07128 Retrofitting Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method) and Rising Main for Additional T/W of TAPSHIKHATA Piped Water Supply Scheme Under Alipurduar Division PHE DTE Alipurduar RWS RWS Alipurduar - I Block ORD/000321/2021-2022 2197/ALD 11/01/2022 90 DEBABRATA DUTTA 21.58 4.43 20.53 68.67
4 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Tapshikatha Piped Water Supply Scheme (Phase-2) , SM/07128 Retrofitting Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Tapshikhata WSS under Alipurduar Division, PHE Dte. Part-6 Alipurduar RWS RWS Alipurduar - I Block ORD/000350/2021-2022 2143/ALD 06/01/2022 30 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 5.03 0.00 0 76
5 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Tapshikatha Piped Water Supply Scheme (Phase-2) , SM/07128 Retrofitting Extension of pipeline (UPVC) and providing FHTC at surrounding area of Tapshikhata PWSS Under Alipurduar Division, PHE DTE. Alipurduar RWS RWS Alipurduar - I Block ORD/000442/2021-2022 2750/ALD 24/02/2022 60 AMBITIOUS ENTERPRISE 36.94 0.00 0 68
6 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Tapshikatha Piped Water Supply Scheme (Phase-2) , SM/07128 Retrofitting Withdrawing and relaying of UPVC and DI pipeline due to damaged during bitumen road construction and other misc works at Tapshikhata PWSS under Alipurduar Division, PHE Dte. Alipurduar RWS RWS Alipurduar - I Block ORD/000146/2020-2021 941/ALD 19/10/2020 60 KAMALESH ROY 10.81 0.00 0 76.5
7 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Tapshikatha Piped Water Supply Scheme (Phase-2) , SM/07128 Retrofitting Providing extension of distribution line, AT TAPSHIKATHA G.P from the commissioned TAPSHIKATHA PWSS (UID-APD-022) UNDER ALIPURDUAR DIVISION PHE DTE. Alipurduar RWS RWS Alipurduar - I Block ORD/000308/2020-2021 1481/ALD 27/01/2021 60 KAMALESH ROY 12.16 2.26 18.59 75.5
8 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Tapshikatha Piped Water Supply Scheme (Phase-2) , SM/07128 Retrofitting Extension and replacement of damaged pipeline including new FHTC under Dakshin Chakoakhati mouza (Simlabari area) at Alipurduar-I Block under Alipurduar Division, PHE Dte. Alipurduar RWS,HQ-A.E RWS Alipurduar - I Block,RWS Kalchini Block ORD/000078/2021-2022 876/ALD 03/09/2021 60 M/S AMIT KUMAR GUPTA 35.43 0.00 0 75.2
Total 181.89 31.59 17.37