Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 211.04 73.3 34.73  
1 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Lankapara Water Supply Scheme (Phase-2) , SM/07066 Retrofitting Providing House connection at LANKAPARA TG (Part-A) PWSS under Alipuduar Division, P.H.E. Dte. Birpara A.E Birpara Sub Division ORD/000364/2020-2021 1807/ALD 22/02/2021 60 GHOSH & SAHA CONSTRUCTION 41.88 10.17 24.28 45
2 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Lankapara Water Supply Scheme (Phase-2) , SM/07066 Retrofitting Laying of HDPE/DI pipe line at different area of flank of Lankapara road/village road and Lankapara Bazar Area under Alipurduar Division, PHE Dte. Birpara A.E Birpara Sub Division ORD/000182/2020-2021 1007/ALD 12/11/2020 60 MADHAB SAHA 33.79 13.13 38.86 98.5
3 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Lankapara Water Supply Scheme (Phase-2) , SM/07066 Retrofitting Laying of DI/MS/HDPE Distribution pipe line for the LANKAPARA WSS (TULSHIPARA TG) under Alipurduar Division, PHE Dte. Dist-Alipurduar. Birpara A.E Birpara Sub Division ORD/000268/2020-2021 1280/ALD 05/01/2021 60 UMWELT ENGINEER PVT. LTD. 30.90 0.00 0 98
4 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Lankapara Water Supply Scheme (Phase-2) , SM/07066 Retrofitting Sinking of 1no. Tube Well for replacement and another 1no. new Tube Well near factory line by ODEX-195 method of drilling at Lankapara Water Supply Scheme under Alipurduar Division, PHE Dte. Birpara A.E Birpara Sub Division ORD/000205/2021-2022 1345/ALD 08/10/2021 30 SASANKA ROY 33.00 32.32 97.94 96
5 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Lankapara Water Supply Scheme (Phase-2) , SM/07066 Retrofitting Development of rig Bore TW by ODEX-165 method of drilling at Lankapara WSS under Alipurduar Division, PHE Dte. Birpara A.E Birpara Sub Division ORD/000261/2021-2022 1608/ALD 22/11/2021 20 DILIP MAHATO 0.66 0.50 75.76 98.5
6 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Lankapara Water Supply Scheme (Phase-2) , SM/07066 Retrofitting Construction of Boundary wall near head work site of Lankapara PWSS under Alipurduar Division, PHE Dte. Birpara A.E Birpara Sub Division ORD/000395/2021-2022 2309/ALD 25/01/2022 45 ASHOK SAPKOTA 4.78 3.04 63.6 98
7 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Lankapara Water Supply Scheme (Phase-2) , SM/07066 Retrofitting Construction of Pump House with sanitary & plumbing arrangement near head work site of Lankapara PWSS under Alipurduar Division, PHE Dte. Birpara A.E Birpara Sub Division ORD/000396/2021-2022 2310/ALD 25/01/2022 60 ASHOK SAPKOTA 5.03 4.68 93.04 98
8 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Lankapara Water Supply Scheme (Phase-2) , SM/07066 Retrofitting Construction of balance portion of boundary wall at CWR site under LANKAPARA (TULSHIPARA TG ) WSS under Alipurduar Division PHE Dte . Birpara A.E Birpara Sub Division ORD/000084/2022-2023 448/ALD 13/05/2022 30 TAPASH KUMAR BHOWMICK 4.91 4.80 97.76 96.5
9 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Lankapara Water Supply Scheme (Phase-2) , SM/07066 Retrofitting Bridge Crossing and Laying of DI/MS/HDPE Distribution pipe line for the LANKAPARA WSS under Alipurduar Division, PHE Dte. Dist-Alipurduar. Birpara A.E Birpara Sub Division ORD/000270/2020-2021 1282/ALD 05/01/2021 60 GHOSH & SAHA CONSTRUCTION 23.75 4.66 19.62 100
10 ALIPURDUAR Alipurduar Division F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Lankapara Water Supply Scheme (Phase-2) , SM/07066 Retrofitting Sinking of Rig Bore Tube well by Odex-165 method of drilling and installation of Raising Main and laying of DI/MS/HDPE pipe line for the Tulshipara and Lankapara Water Supply Scheme. Birpara A.E Birpara Sub Division ORD/000181/2020-2021 1006/ALD 12/11/2020 60 UMWELT ENGINEER PVT. LTD. 32.34 0.00 0 97
Total 211.03 73.29 34.73