1 |
ALIPURDUAR |
|
Alipurduar Division |
FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of UTTAR SISHUBARI Water Supply Scheme , SM/08881 |
Retrofitting |
Replacement of old existing AC pipeline with UPVC pipe and providing FHTC in connection with Jaldhara/Jal Sapna for Uttar Sishubari WSS under Alipurduar Division, PHE Dte. (Opposite of Rail line area) |
Birpara A.E |
Alipurduar Sub Division,Birpara Sub Division |
ORD/000236/2021-2022 |
1577/ALD |
22/11/2021 |
60 |
ASHOK SAPKOTA |
22.55 |
20.81 |
92.28 |
54 |
2 |
ALIPURDUAR |
|
Alipurduar Division |
FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of UTTAR SISHUBARI Water Supply Scheme , SM/08881 |
Retrofitting |
Replacement of old existing AC pipeline with UPVC pipe and providing FHTC in connection with Jaldhara/Jal Sapna for Uttar Sishubari WSS under Alipurduar Division, PHE Dte. (Opposite of Rail line area) |
Alipurduar Sadar Sub Division,Birpara A.E |
Alipurduar Sub Division,Birpara Sub Division |
ORD/000237/2021-2022 |
1578/ALD |
22/11/2021 |
60 |
KAMALESH ROY |
22.55 |
20.81 |
92.28 |
55 |
3 |
ALIPURDUAR |
|
Alipurduar Division |
FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of UTTAR SISHUBARI Water Supply Scheme , SM/08881 |
Retrofitting |
Laying of UPVC/DI/MS/CI Distribution pipe line for Gap filling of Chapaguri area at Uttar Sishubari PWSS under Alipurduar Division PHE Dte. |
Birpara A.E |
Birpara Sub Division |
ORD/000435/2021-2022 |
2652/ALD |
21/02/2022 |
45 |
KAMALESH ROY |
4.94 |
4.68 |
94.74 |
55 |
4 |
ALIPURDUAR |
|
Alipurduar Division |
FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of UTTAR SISHUBARI Water Supply Scheme , SM/08881 |
Retrofitting |
Construction of boundary wall at 2nd PH Site of Uttar Sishubari WSS under Alipurduar Division.
|
Birpara A.E |
Birpara Sub Division |
ORD/000096/2021-2022 |
895/ALD |
03/09/2021 |
45 |
MITHUN DAS |
4.98 |
1.42 |
28.51 |
56 |
5 |
ALIPURDUAR |
|
Alipurduar Division |
FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of UTTAR SISHUBARI Water Supply Scheme , SM/08881 |
Retrofitting |
Extension/Merging of Distribution pipeline (UPVC/DI/MS/CI) from Paschim Khairbari WSS to Uttar Sishubari WSS and others misc. work under Alipurduar Division, PHE Dte. |
Birpara A.E |
Birpara Sub Division |
ORD/000264/2020-2021 |
1255/ALD |
28/12/2020 |
60 |
MITHUN DAS |
45.83 |
9.00 |
19.64 |
80 |
6 |
ALIPURDUAR |
|
Alipurduar Division |
FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of UTTAR SISHUBARI Water Supply Scheme , SM/08881 |
Retrofitting |
Material Requisition To Resource Division |
|
|
RTOR000013/2022-2023 |
718/ALD |
13/06/2022 |
0 |
Resource Division |
87.66 |
0.00 |
0 |
0 |
7 |
ALIPURDUAR |
|
Alipurduar Division |
FHTC under Jaldhara Jalswapna Including Retrofitting of existing distribution system under the command area of UTTAR SISHUBARI Water Supply Scheme , SM/08881 |
Retrofitting |
Repairing of 2 nos. P/H with toilet block (PH-1 and 2) and Replacement of old existing AC p/l with UPVC pipe and providing FHTC in connection with Jaldhara/Jal Sapna for Uttar Sishubari WSS under Alipurduar Division, PHE Dte. (Sishubari High School and adjacent area) |
Birpara A.E |
Alipurduar Sub Division,Birpara Sub Division |
ORD/000179/2021-2022 |
1309/ALD |
05/10/2021 |
60 |
MITHUN DAS |
45.40 |
18.14 |
39.96 |
100 |