1 |
ALIPURDUAR |
|
Alipurduar Division |
F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Radharani T.G Water Supply Scheme (Phase-1) , SM/07067 |
Retrofitting |
Laying HDPE pipe , Road crossing and other misc woks related to Radharani WSS under Alipurduar Division PHE Dte.
|
HQ-A.E |
RWS Kalchini Block |
ORD/000272/2021-2022 |
1838/ALD |
10/12/2021 |
45 |
UMWELT ENGINEER PVT. LTD. |
3.01 |
0.00 |
0 |
91 |
2 |
ALIPURDUAR |
|
Alipurduar Division |
F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Radharani T.G Water Supply Scheme (Phase-1) , SM/07067 |
Retrofitting |
Providing FHTC at surrounding area of Radharani Piped Water Supply Scheme Under Alipurduar Division, PHE DTE. |
HQ-A.E |
RWS Kalchini Block |
ORD/000476/2021-2022 |
2762/ALD |
25/02/2022 |
60 |
SOUVIK ROY PALADHI |
34.95 |
0.00 |
0 |
91.5 |
3 |
ALIPURDUAR |
|
Alipurduar Division |
F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Radharani T.G Water Supply Scheme (Phase-1) , SM/07067 |
Retrofitting |
PROVIDING HOUSE CONNECTION FOR RADHARANI PWSS AT KALCHINI BLOCK UNDER ALIPURDUAR DIVISION, PHE DTE. PART-2 |
HQ-A.E |
RWS Kalchini Block |
ORD/000197/2020-2021 |
1028/ALD |
18/11/2020 |
60 |
UMWELT ENGINEER PVT. LTD. |
37.24 |
32.53 |
87.35 |
90.5 |
4 |
ALIPURDUAR |
|
Alipurduar Division |
F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Radharani T.G Water Supply Scheme (Phase-1) , SM/07067 |
Retrofitting |
Balance work of OHR Construction of PHouse B/Wall Godown & ODEX-165 Tubewell incl. laying of DI/HDPE Pipe for Nayabasti SSB Camp at RADHARANI PWSS under Alipurduar Division PHED. |
HQ-A.E |
RWS Kalchini Block |
ORD/000076/2020-2021 |
627/ALD |
03/09/2020 |
120 |
UMWELT ENGINEER PVT. LTD. |
65.53 |
0.00 |
0 |
91.5 |
5 |
ALIPURDUAR |
|
Alipurduar Division |
F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Radharani T.G Water Supply Scheme (Phase-1) , SM/07067 |
Retrofitting |
PROVIDING HOUSE CONNECTION FOR RADHARANI PWSS AT KALCHINI BLOCK UNDER ALIPURDUAR DIVISION, PHE DTE. PART-1 |
HQ-A.E |
RWS Kalchini Block |
ORD/000196/2020-2021 |
1027/ALD |
18/11/2020 |
60 |
UMWELT ENGINEER PVT. LTD. |
37.24 |
22.54 |
60.53 |
92 |
6 |
ALIPURDUAR |
|
Alipurduar Division |
F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Radharani T.G Water Supply Scheme (Phase-1) , SM/07067 |
Retrofitting |
Supply of different materials for Alipurduar divisional stackyard under Alipurduar Division, PHE Dte. |
Alipurduar Sadar Sub Division,Birpara A.E,HQ-A.E |
Alipurduar Sub Division,Birpara Sub Division,RWS Alipurduar - II Block,RWS Kalchini Block |
ORD/000556/2021-2022 |
855/ALD |
31/08/2021 |
30 |
EXECUTIVE ENGINEER, RESOURCE DIVISION |
2,590.66 |
0.00 |
0 |
0 |
7 |
ALIPURDUAR |
|
Alipurduar Division |
F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Radharani T.G Water Supply Scheme (Phase-1) , SM/07067 |
Retrofitting |
Balance work of construction of RADHARANI GODOWN cum REST SHED at RADHARANI WSS under Alipurduar Division , PHE Dte ( Part - A)
|
HQ-A.E |
RWS Kalchini Block |
ORD/000090/2022-2023 |
454/ALD |
13/05/2022 |
30 |
BHAGWATI BHUJEL |
5.02 |
0.00 |
0 |
91.5 |
8 |
ALIPURDUAR |
|
Alipurduar Division |
F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Radharani T.G Water Supply Scheme (Phase-1) , SM/07067 |
Retrofitting |
Construction of Approach Road with paver Block at RADHARANI WSS under Alipurduar Division , PHE Dte
|
HQ-A.E |
RWS Kalchini Block |
ORD/000091/2022-2023 |
455/ALD |
13/05/2022 |
30 |
BHAGWATI BHUJEL |
4.96 |
0.00 |
0 |
91.5 |
9 |
ALIPURDUAR |
|
Alipurduar Division |
F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Radharani T.G Water Supply Scheme (Phase-1) , SM/07067 |
Retrofitting |
Balance work of Radharani Godown cum rest shed under Radharani WSS under Alipurduar Division, PHE Dte. (Part-B)
|
HQ-A.E |
RWS Kalchini Block |
ORD/000186/2022-2023 |
1020/ALD |
21/07/2022 |
30 |
ASHOK PRADHAN |
2.82 |
0.00 |
0 |
89 |
10 |
ALIPURDUAR |
|
Alipurduar Division |
F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Radharani T.G Water Supply Scheme (Phase-1) , SM/07067 |
Retrofitting |
Laying of HDPE pipe line for Bijaynagar Busty Area under Radharani Water Supply Scheme, Alipurduar Division, PHE Dte. |
HQ-A.E |
RWS Kalchini Block |
ORD/000328/2021-2022 |
2201/ALD |
11/01/2022 |
60 |
SOUVIK ROY PALADHI |
41.96 |
33.82 |
80.6 |
91.5 |