| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 5 | 7.66 | 4.84 | 63.19 | ||||||||||||||
| 1 | PURBA MEDINIPUR | Midnapore Mechanical | Solarization of grid connected pumping installation at Dwariberia PWSS in Purba Medinipore District under JJM programme under Midnapore Mechanical Division, PHE Dte. , SM/17761 | Solarisation | Solarization of grid connected pumping installation at Dwariberia PWSS in Purba Medinipore District under JJM programme under Midnapore Mechanical Division, PHE Dte. | Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi | Sri Tanmoy Shee, JE/Haldia Electrical Sub-Division. | ORD/002091/2022-2023 | 1010/W/MMD | 29/03/2023 | 180 | MEGA SOLAR ENERGY | 6.26 | 4.66 | 74.44 | 50 | |
| 2 | PURBA MEDINIPUR | Midnapore Mechanical | Solarization of grid connected pumping installation at Dwariberia PWSS in Purba Medinipore District under JJM programme under Midnapore Mechanical Division, PHE Dte. , SM/17761 | Solarisation | Supply and installation of Sign Board for depicting the scheme details of different ongoing Solarisation/ Rejuvenation/ Other JJM works for the purpose of Geotagging at BARBASUDEBPUR and adjacent under MMD, P.H.E. Dte.Dist.- Purba Medinipur. | Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi | Sri Tanmoy Shee, JE/Haldia Electrical Sub-Division. | ORD/000065/2024-2025 | 535/HESD | 10/06/2024 | 15 | KOLEY ENTERPRISE | 1.23 | 0.18 | 14.63 | 75 | |
| 3 | PURBA MEDINIPUR | Midnapore Mechanical | Solarization of grid connected pumping installation at Dwariberia PWSS in Purba Medinipore District under JJM programme under Midnapore Mechanical Division, PHE Dte. , SM/17761 | Solarisation | Quotation bill for application fees for NET BILLING for solar power plant of 10KWp at Dwariberia w/s scheme,Block-sutahata in the Dist. of Purba Medinipur under MMD,PHE,Dte. Name of C.C.C.-Chaitanyapur Application no-2004837078 Consumer ID-224041892 Quotation Date-25/07/2024 Quotation Due Date-90days from the date of issue | BILL/01864/2024-2025 | BP-2024-25-550 | 07/08/2024 | 0 | WBSEDCL | 0.01 | 0.00 | 0 | 0 | |||
| 4 | PURBA MEDINIPUR | Midnapore Mechanical | Solarization of grid connected pumping installation at Dwariberia PWSS in Purba Medinipore District under JJM programme under Midnapore Mechanical Division, PHE Dte. , SM/17761 | Solarisation | Quotation Bill for Application Fee for NET METERING at Dwariberia w/s scheme Block-Haldia under MMD,PHE Dte. Name of CCC-Chaitanyapur Application number -2005183908 Consumer ID-224041892 Quotation Issuance Date-22/04/2025 Quotation valid for 90days from the date of issue | BILL/00711/2025-2026 | 08/05/2025 | 0 | WBSEDCL | 0.01 | 0.00 | 0 | 0 | ||||
| 5 | PURBA MEDINIPUR | Midnapore Mechanical | Solarization of grid connected pumping installation at Dwariberia PWSS in Purba Medinipore District under JJM programme under Midnapore Mechanical Division, PHE Dte. , SM/17761 | Solarisation | Quotation bill for Net Meter for solar plant at TW-I of Dwariberia w/s scheme, Block-Haldia, in the Dist. of Purba Medinipur under MMD,PHE Dte. Name of C.C.C-Chaitanyapur Application No.-2005541253 Con. ID-224041892 Contractual load-11.19 KW Installed capacity of solar plant-10.3 kWP Quotation Date -01/12/2025 | BILL/03858/2025-2026 | 16/12/2025 | 0 | WBSEDCL | 0.15 | 0.00 | 0 | 0 | ||||
| Total | 7.65 | 4.84 | 63.24 | ||||||||||||||