Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
3 | 126.14 | 0 | 0 | ||||||||||||||
1 | PURBA MEDINIPUR | Tamluk Division | Retrofitting to Accommodate FHTC under JJM in Arjunnagar PWSS under Bhagwanpur-II Block (Phase-II) , SM/16453 | Retrofitting | Material Requisition To Resource Division | RTOR000060/2023-2024 | 2636/TD | 13/10/2023 | Resource Division | 8.14 | 0.00 | 0 | 0 | ||||
2 | PURBA MEDINIPUR | Tamluk Division | Retrofitting to Accommodate FHTC under JJM in Arjunnagar PWSS under Bhagwanpur-II Block (Phase-II) , SM/16453 | Retrofitting | Material Requisition To Resource Division | RTOR000058/2023-2024 | 2096/TD | 29/08/2023 | Resource Division | 26.91 | 0.00 | 0 | 0 | ||||
3 | PURBA MEDINIPUR | Tamluk Division | Retrofitting to Accommodate FHTC under JJM in Arjunnagar PWSS under Bhagwanpur-II Block (Phase-II) , SM/16453 | Retrofitting | Providing 1321 Nos FHTC (Functional Household Tap Connection) with allied works of Arjunnagar & its adjoining mouzas Water Supply Scheme under Bhagawanpur-II Block under Contai Sub Division of Tamluk Division, PHE DTe.Purba Medinipur (Phase -II) | Junior Engineer | ORD/000401/2023-2024 | 1069/TD | 08/06/2023 | 45 | TAPAS SANTRA | 91.09 | 0.00 | 0 | 0 | ||
Total | 126.14 | 0.00 | 0 |