Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 271.34 96.36 35.51  
1 PURBA MEDINIPUR Tamluk Division Piped Water Supply Scheme for Sankarpur Zone-IV , SM/16305 Augmentation Material Requisition To Resource Division RTOR000047/2023-2024 2070/TD 28/08/2023 0 Resource Division 14.46 0.00 0 0
2 PURBA MEDINIPUR Tamluk Division Piped Water Supply Scheme for Sankarpur Zone-IV , SM/16305 Augmentation Material Requisition To Resource Division RTOR000096/2023-2024 2999/TD 29/11/2023 0 Resource Division 1.81 0.00 0 0
3 PURBA MEDINIPUR Tamluk Division Piped Water Supply Scheme for Sankarpur Zone-IV , SM/16305 Augmentation Sinking of Tube Well, Laying distribution pipe line, Pump House, Boundary Wall soil investigation, 250 Cum OHR & Accommodate FHTC ( 294 Nos) under JJM with allied work for SANKARPUR (Zone-IV) PWSS within Ramnagar-I Block under Digha Sub-Division of Tamluk Division , PHED , Purba Medinipur Assistant Engineer Junior Engineer ORD/000510/2023-2024 1732/TD 31/07/2023 610 ONKAR ENTERPRISE 216.84 69.71 32.15 55
4 PURBA MEDINIPUR Tamluk Division Piped Water Supply Scheme for Sankarpur Zone-IV , SM/16305 Augmentation Preparation of D.P.R. for different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Sankarpur Water Supply Scheme (Zone- IV) under Tamluk Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000331/2023-2024 741/TD 25/05/2023 20 ASTER CONSULTANCY 3.46 3.46 100 100
5 PURBA MEDINIPUR Tamluk Division Piped Water Supply Scheme for Sankarpur Zone-IV , SM/16305 Augmentation Preparation of design based on soil test report and submission of drawing of foundation for construction of 250 cum RCC OHR at Sankarpur Z-IV PWSS at Ramnagar-I Block under Tamluk Division,PHE Dte. Assistant Engineer Junior Engineer ORD/001281/2023-2024 1053/TD 15/03/2024 10 GEOTECHNICAL ENGINEERS CONSORTIUM 0.95 0.95 100 100
6 PURBA MEDINIPUR Midnapore Mechanical Piped Water Supply Scheme for Sankarpur Zone-IV , SM/16305 Augmentation Sankarpur W/S scheme PH.-II, zone-IV Application No.-2004565718 Ref.-204193727 BILL/03540/2023-2024 BP-2023-24-622 07/02/2024 0 WBSEDCL 7.26 0.00 0 0
7 PURBA MEDINIPUR Midnapore Mechanical Piped Water Supply Scheme for Sankarpur Zone-IV , SM/16305 Augmentation Sankarpur W/S scheme TW no.-I, Z-IV Ref.-204156071 Application ID-2004521698 BILL/03156/2023-2024 BP-2023-24-442 19/12/2023 0 WBSEDCL 2.63 0.00 0 0
8 PURBA MEDINIPUR Midnapore Mechanical Piped Water Supply Scheme for Sankarpur Zone-IV , SM/16305 Augmentation Providing and Installation of Submersible pumping machineries and other electromechanical equipments atPiped Water Supply Scheme for Sankarpur Zone-IV in Purba Medinipur District, under JJM Program under MMD PHE Dte. Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi Sri Mrityunjoy Paria, JE/Haldia Electrical Sub-Division ORD/000041/2023-2024 1212/W/MMD 25/04/2023 180 SUBHASIS ROY 23.93 22.24 92.94 90
Total 271.35 96.36 35.51