Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
5 | 341.92 | 2.89 | 0.85 | ||||||||||||||
1 | PURBA MEDINIPUR | Midnapore Mechanical | Piped Water Supply Scheme for Chirulia-Chatla Zone-4 , SM/15844 | Augmentation | Providing and Installation of Submersible pumping machineries and other electromechanical equipments at different PWSS of Block Egra - I in Purba Medinipur District, under JJM Program under MMD PHE Dte. | Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi | Sri Mrityunjoy Paria, JE/Haldia Electrical Sub-Division | ORD/000050/2023-2024 | 1207/W/MMD | 25/04/2023 | 180 | BHABANI PRASAD MANNA | 59.85 | 0.00 | 0 | 0 | |
2 | PURBA MEDINIPUR | Tamluk Division | Piped Water Supply Scheme for Chirulia-Chatla Zone-4 , SM/15844 | Augmentation | Sinking of Tube Well, Laying distribution pipe line, Pump House, Boundary Wall soil investigation, 250 Cum OHR & Accommodate FHTC ( 173 Nos) under JJM with allied work for Chirulia-Chatla (Zone-IV) PWSS within Egra-I Block under Digha Sub-Division of Tamluk Division , PHED , Purba Medinipur. | Assistant Engineer | Junior Engineer | ORD/000523/2023-2024 | 1759/TD | 01/08/2023 | 180 | SUSIL KUMAR HAZRA | 262.49 | 0.00 | 0 | 0 | |
3 | PURBA MEDINIPUR | Tamluk Division | Piped Water Supply Scheme for Chirulia-Chatla Zone-4 , SM/15844 | Augmentation | Preparation of D.P.R. for different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Chirulia Chatla Water Supply Scheme (Zone-IV) under Tamluk Division, PHE Dte. | Assistant Engineer | Junior Engineer | ORD/000496/2022-2023 | 1932./TD | 28/11/2022 | 20 | ASTER CONSULTANCY | 3.46 | 2.89 | 83.53 | 100 | |
4 | PURBA MEDINIPUR | Tamluk Division | Piped Water Supply Scheme for Chirulia-Chatla Zone-4 , SM/15844 | Augmentation | Material Requisition To Resource Division | RTOR000051/2023-2024 | 2076/TD | 28/08/2023 | Resource Division | 15.05 | 0.00 | 0 | 0 | ||||
5 | PURBA MEDINIPUR | Tamluk Division | Piped Water Supply Scheme for Chirulia-Chatla Zone-4 , SM/15844 | Augmentation | Material Requisition To Resource Division | RTOR000093/2023-2024 | 2996/TD | 29/11/2023 | Resource Division | 1.07 | 0.00 | 0 | 0 | ||||
Total | 341.91 | 2.89 | 0.85 |