Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
14 21,745.97 165.31 0.76  
1 PURBA MEDINIPUR Bhagawanpur-II Tamluk Division BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Material Requisition To Resource Division RTOR000120/2022-2023 2389/TD 16/01/2023 0 Resource Division 33.31 0.00 0 0
2 PURBA MEDINIPUR Bhagawanpur-II Tamluk Division BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Laying distribution pipe line & Accommodate FHTC (60 nos) under JJM with allied work of BASUDEB BERYA PWSS within Bhagwanpur-II Block under Contai Sub-Division of Tamluk Division, PHE Dte.(PART - F) Assistant Engineer Junior Engineer ORD/000844/2022-2023 3187/TD 10/03/2023 15 SUSANTA KUMAR KAR 9.80 4.36 44.49 45
3 PURBA MEDINIPUR Bhagawanpur-II Tamluk Division BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Laying distribution pipe line & Accommodate FHTC (300nos) under JJM with allied work of BASUDEB BERYA PWSS within Bhagwanpur-II Block under Contai Sub-Division of Tamluk Division, PHE Dte.(PART - D) Assistant Engineer Junior Engineer ORD/000843/2022-2023 3186/TD 10/03/2023 25 BADAL CHANDRA GOLE 37.34 16.56 44.35 48
4 PURBA MEDINIPUR Bhagawanpur-II Tamluk Division BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Pump House, Laying distribution pipe line, & Accommodate FHTC (270 nos) under JJM with allied work of BASUDEB BERYA PWSS within Bhagwanpur-II Block under Contai Sub-Division of Tamluk Division, PHE Dte. (PART-B) Assistant Engineer Junior Engineer ORD/000840/2022-2023 3184/TD 10/03/2023 25 SUBHENDU HAZRA 48.38 23.10 47.75 50
5 PURBA MEDINIPUR Bhagawanpur-II Tamluk Division BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Pump House ,150 cum OHR (Intze type with pile foundation), Rising main, Head work site, Laying distribution pipe line, Boundary Wall, Soil investigation & Accommodate FHTC (124 nos) under JJM with allied work of BASUDEB BERYA PWSS within Bhagwanpur-II Block under Contai Sub-Division of Tamluk Division, PHE Dte. (PART- A) Assistant Engineer Junior Engineer ORD/000382/2023-2024 1018/TD 06/06/2023 936 DAS ENTERPRISE 201.92 70.87 35.1 37
6 PURBA MEDINIPUR Bhagawanpur-II Tamluk Division BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Preparation of design based on soil test report and submission of drawing of foundation for construction of 150 cum RCC OHR at Basudeb Berya PWSS at Bhagwanpur-II Block under Tamluk Division,PHE Dte. Assistant Engineer ORD/001052/2023-2024 382/TD 29/01/2024 10 GEOTECHNICAL ENGINEERS CONSORTIUM 0.95 0.95 100 100
7 PURBA MEDINIPUR Bhagawanpur-II Tamluk Division BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Material Requisition To Resource Division RTOR000185/2023-2024 634/W 20/02/2024 0 Resource Division 6.55 0.00 0 0
8 PURBA MEDINIPUR Bhagawanpur-II Midnapore Mechanical BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Additional Quotation Bill cost due to Modification for NSC of PHE AT Site- BASUDEVBERIA W/S SCHEME, T/W NO-I Under Jal Jeevan Mission under MMD, PHE, Dte. Block- BHAGWANPUR-II, WBSEDCL SUPPLY OFFICE: MADHAKHALI C.C.C. Ref. Memo No-MDK/QOUT/253 DT. 16-05-2024 Application NO- 100000108115 DT. 16-05-2024 Application type-ADDITIONAL QUOTATION REF. Id- 860300165 BILL/01128/2024-2025 BP-2024-25-241 06/06/2024 0 WBSEDCL 0.59 0.00 0 0
9 PURBA MEDINIPUR Bhagawanpur-II Midnapore Mechanical BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Quotation Bill for New Service connection at T/W NO-II Of BASUDEVBERIA W/S Scheme under MMD, PHE, Dte. Block- Bhagwanpur-II, MADHAKHALI C.C.C. Ref. Memo No- 2004558723/QUOT/03 DT. 10-01-2024 Application NO- 2004558723 Application type-New connection Consumer Id- 204187848 BILL/04388/2023-2024 BP-2023-24-829 13/03/2024 0 WBSEDCL 3.14 0.00 0 0
10 PURBA MEDINIPUR Bhagawanpur-II Midnapore Mechanical BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Quotation Bill for New Service connection at T/W NO-I Of BASUDEVBERIA W/S Scheme under MMD, PHE, Dte. Block- Bhagwanpur-II, MADHAKHALI C.C.C. Ref. Memo No- 2004558731/QUOT/03 DT. 27-02-2024 Application NO- 2004558731 Application type-New connection Consumer Id- 204187847 BILL/04390/2023-2024 BP-2023-24-828 13/03/2024 0 WBSEDCL 3.48 0.00 0 0
11 PURBA MEDINIPUR Bhagawanpur-II Tamluk Division BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Laying distribution pipe line, Boundary Wall & Accommodate FHTC ( 250 nos) under JJM with allied work of BASUDEB BERYA PWSS within Bhagwanpur-II Block under Contai Sub-Division of Tamluk Division, PHE Dte.(PART - C) Assistant Engineer Junior Engineer ORD/000841/2022-2023 3185/TD 10/03/2023 635 M/S. NEW DINDA ENTERPRISE 48.13 23.70 49.24 50
12 PURBA MEDINIPUR Bhagawanpur-II Central Drilling BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 304 JHARGRAM SPV PRIVATE LIMITED 21,339.76 25.77 0.12 11
13 PURBA MEDINIPUR Bhagawanpur-II Midnapore Mechanical BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Construction of materials godown alongwith internal electrification and illumination and other works at the campus of the office of Assistant Engineer under HESD, PHE Dte., Dist.- Purba Medinipur. Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi Sri Mrityunjoy Paria, JE/Haldia Electrical Sub-Division ORD/002725/2023-2024 1070/W/MMD 14/03/2024 180 THE GODFATHER TRADING COMPANY 10.42 0.00 0 100
14 PURBA MEDINIPUR Bhagawanpur-II Midnapore Mechanical BASUDEVBERYA AND ADJOINING MOUJAS PWSS , SM/12297 New Supply and fitting fixing of porcelain fuse unit and aluminum armored cable for receiving service connection at different PWSS under Egra-II, Bhagwanpur-I and II Block under Medinapore Mechanical Division, P.H.E. Dte. in the dist. of Purba Medinipur. Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi Sri Sukanta Mondal, JE/Haldia Electrical Sub-Division. ORD/000130/2024-2025 702/HESD 19/07/2024 227 SOUMEN ELECTRIC 2.20 0.00 0 70
Total 21,745.98 165.31 0.76