Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 22,087.42 453.17 2.05  
1 PURBA MEDINIPUR Khejuri-I Tamluk Division AJAYA & ADJOINING MOUJAS PWSS , SM/12174 New Material Requisition To Resource Division RTOR000339/2022-2023 2976/TD 27/02/2023 0 Resource Division 32.62 0.00 0 0
2 PURBA MEDINIPUR Khejuri-I Tamluk Division AJAYA & ADJOINING MOUJAS PWSS , SM/12174 New Material Requisition To Resource Division RTOR000066/2024-2025 2946/TD 12/09/2024 0 Resource Division 11.38 0.00 0 0
3 PURBA MEDINIPUR Khejuri-I Midnapore Mechanical AJAYA & ADJOINING MOUJAS PWSS , SM/12174 New Ajaya W/S scheme T/W -II Application No.-2004565730 Ref.-204193622 BILL/03476/2023-2024 BP-2023-24-592 02/02/2024 0 WBSEDCL 8.24 0.00 0 0
4 PURBA MEDINIPUR Khejuri-I Midnapore Mechanical AJAYA & ADJOINING MOUJAS PWSS , SM/12174 New Ajaya W/S scheme T/W -I Application No.-2004565721 Ref.-204193605 BILL/03475/2023-2024 BP-2023-24-593 02/02/2024 0 WBSEDCL 3.19 0.00 0 0
5 PURBA MEDINIPUR Khejuri-I Central Drilling AJAYA & ADJOINING MOUJAS PWSS , SM/12174 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 304 JHARGRAM SPV PRIVATE LIMITED 21,339.76 7.83 0.04 11
6 PURBA MEDINIPUR Khejuri-I Tamluk Division AJAYA & ADJOINING MOUJAS PWSS , SM/12174 New Tube well,Pump House ,250 cum OHR (Intze type with pile foundation), Rising main, Head work site, Laying distribution pipe line, Boundary Wall, Soil investigation & Accommodate FHTC (1847 nos) under JJM with allied work for AJAYA- PWSS in Khejuri-I Block within Contai Sub-Division under Tamluk Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000474/2023-2024 1515/TD 17/07/2023 807 TAPAS SANTRA 664.53 432.68 65.11 70
7 PURBA MEDINIPUR Khejuri-I Midnapore Mechanical AJAYA & ADJOINING MOUJAS PWSS , SM/12174 New Providing and Installation of Submersible pumping machineries and other electromechanical equipments for Ground Water Based Piped Water Supply Scheme for AJAYA and ADJOINING MOUJAS, Block ¿ Khejuri I, District - Purba Medinipurunder JJM Program under MMD PHE Dte. Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi Sri Krishanu Mondal, JE/Haldia Electrical Sub-Division. ORD/002290/2022-2023 2384/W/MMD 31/12/2022 180 P.K.ENGINEERING 27.70 12.66 45.7 45
Total 22,087.42 453.17 2.05