Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
3 126.12 72.39 57.4  
1 PURBA MEDINIPUR Tamluk Division Retrofitting to accomodate FHTC under JJM in Paya(Mahaprabhu) W/S Scheme , SM/08232 Retrofitting Retrofitting to accommodate FHTC under JJM in Paya(Mahaprabhu) PWSS Block- Ramnagar-I in the District of Purba Medinipur.(Phase-II) Assistant Engineer Junior Engineer ORD/000280/2020-2021 2996/TD 25/02/2021 30 MAITY CONSTRUCTION 99.11 72.39 73.04 100
2 PURBA MEDINIPUR Tamluk Division Retrofitting to accomodate FHTC under JJM in Paya(Mahaprabhu) W/S Scheme , SM/08232 Retrofitting Retrofitting to accomodate FHTC under JJM Paya (Mahaprabhu) W/S Scheme under Tamluk Division, PHE Dte. VCH/001108/2020-2021 1087/W 30/03/2021 0 MAITY CONSTRUCTION 24.87 0.00 0 0
3 PURBA MEDINIPUR Tamluk Division Retrofitting to accomodate FHTC under JJM in Paya(Mahaprabhu) W/S Scheme , SM/08232 Retrofitting valve operator (one no) in head work site at Paya(Mahaprabhu) & its adjoining mouzas water supply scheme within Ramnagar-I Block under Digha Sub-Division of Tamluk Division PHE Dte. (For 12 months or 365 days) w.e.f from 01.09.2024 ORD/000248/2024-2025 873/DSD 27/08/2024 365 MAITY CONSTRUCTION 2.14 0.00 0 0
Total 126.12 72.39 57.4