Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 36.49 0 0  
1 PURBA MEDINIPUR Chandipur Tamluk Division Newly setup Digha Sub-Divisional Laboratory within the Compound of Headwork Site of Digha Augmentation W/S Scheme (Eastern Zone) under Digha Sub-Division of Tamluk Division, PHE Dte. , SM/06651 New Different work under Tamluk Division, PHE Dte. VCH/000165/2020-2021 05 16/04/2020 0 DIFFERENT CONTRACTOR OF TAMLUK DIVISION, PHE DTE. 9.82 0.00 0 0
2 PURBA MEDINIPUR Chandipur Tamluk Division Newly setup Digha Sub-Divisional Laboratory within the Compound of Headwork Site of Digha Augmentation W/S Scheme (Eastern Zone) under Digha Sub-Division of Tamluk Division, PHE Dte. , SM/06651 New Different work under Tamluk Division, PHE Dte. VCH/000166/2020-2021 06 16/04/2020 0 DIFFERENT CONTRACTOR OF TAMLUK DIVISION, PHE DTE. 8.25 0.00 0 0
3 PURBA MEDINIPUR Chandipur Tamluk Division Newly setup Digha Sub-Divisional Laboratory within the Compound of Headwork Site of Digha Augmentation W/S Scheme (Eastern Zone) under Digha Sub-Division of Tamluk Division, PHE Dte. , SM/06651 New Annual Maintenance of Computer and Peripherals for different laboratories in Purba Medinipur District under Tamluk Division, PHE Dte. (Period from 01/11/20 to 28/02/2021) VCH/000074/2021-2022 08/W 05/05/2021 0 MISHRA ENTERPRISE 0.78 0.00 0 0
4 PURBA MEDINIPUR Chandipur Tamluk Division Newly setup Digha Sub-Divisional Laboratory within the Compound of Headwork Site of Digha Augmentation W/S Scheme (Eastern Zone) under Digha Sub-Division of Tamluk Division, PHE Dte. , SM/06651 New Contigency Bill of NGO managed laboratory for the period from October, 2020 to March, 2021. under Tamluk Division, PHE Dte. VCH/000215/2021-2022 161/W 30/07/2021 0 TAMRALIPTA GUCHHA SAMITY AND OTHERS 2.45 0.00 0 0
5 PURBA MEDINIPUR Chandipur Tamluk Division Newly setup Digha Sub-Divisional Laboratory within the Compound of Headwork Site of Digha Augmentation W/S Scheme (Eastern Zone) under Digha Sub-Division of Tamluk Division, PHE Dte. , SM/06651 New Instrument / Equipment for Digha Sub-Divisional Water Testing Laboratory under Digha Sub-Division of Tamluk Division, PHE Dte. VCH/001059/2020-2021 1115/W 30/03/2021 0 LABARD INSTRUCHEM PVT. LTD. 8.06 0.00 0 0
6 PURBA MEDINIPUR Chandipur Tamluk Division Newly setup Digha Sub-Divisional Laboratory within the Compound of Headwork Site of Digha Augmentation W/S Scheme (Eastern Zone) under Digha Sub-Division of Tamluk Division, PHE Dte. , SM/06651 New THIS BILL HAS BEEN RAISED FOR SURRENDER OF UNSPENT FUND TO THE SINGLE NODAL ACCOUNT AS PER CLAUSE 2(III) OF D.O. NO. F.1(13)PFMS/FCD/2020, DTD. 12TH APRIL, 2021 BY SECRETARY, EXPENDITURE, GOVT. OF INDIA, MINISTRY OF FINANCE, DEPARTMENT OF EXPENDITURE AND CLAUSE 13 OF OFFICE MEMORANDUM. NO. F.I. (13) PFMS FCD / 2020 DTD. 23/03/2021 BY THE DIRECTOR (FCD), GOVT. OF INDIA, MINISTRY OF FINANCE, DEPARTMENT OF EXPENDITURE, PFMS DIVISION, AND VIDE MEMO NO. 2724/PHE-13011/7/2021-BUDGET CELL-DEPT. OF PHE Dte. VCH/000706/2021-2022 452/W 22/12/2021 0 JAL JEEVAN MISSION WEST BENGAL ESCROW ACCOUNT 7.13 0.00 0 0
Total 36.49 0.00 0