Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 1,188.51 277.39 23.34  
1 PASCHIM MEDINIPUR Kharagpur-II Midnapore Division RADHAKISHOR AND ITS ADJOINING MOUZAS PWSS , SM/18526 New Material Requisition To Resource Division RTOR000104/2022-2023 207/MD 16/01/2023 0 Resource Division 76.02 0.00 0 0
2 PASCHIM MEDINIPUR Kharagpur-II Midnapore Division RADHAKISHOR AND ITS ADJOINING MOUZAS PWSS , SM/18526 New Material Requisition To Resource Division RTOR000085/2024-2025 3437/MD 25/11/2024 0 Resource Division 21.41 0.00 0 0
3 PASCHIM MEDINIPUR Kharagpur-II Midnapore Mechanical RADHAKISHOR AND ITS ADJOINING MOUZAS PWSS , SM/18526 New Quotation for new power connection at Radhakishore PWSS T/W - II under KGP - II block , Application No- 2004799279, Ref No- 204344494 BILL/01807/2024-2025 BP-2024-25-525 06/08/2024 0 WBSEDCL 6.95 0.00 0 0
4 PASCHIM MEDINIPUR Kharagpur-II Midnapore Mechanical RADHAKISHOR AND ITS ADJOINING MOUZAS PWSS , SM/18526 New Quotation for new power connection at Radhakishore PWSS T/W - I Khargpur - II Block, Application No - 2004799343 , Ref ID : 204344492 BILL/02016/2024-2025 BP-2024-25-585 20/08/2024 0 WBSEDCL 4.95 0.00 0 0
5 PASCHIM MEDINIPUR Kharagpur-II Midnapore Mechanical RADHAKISHOR AND ITS ADJOINING MOUZAS PWSS , SM/18526 New Providing and Installation of Submersible pumping machineries and other electromechanical equipments for RADHAKISHOR AND ITS ADJOINING MOUZAS PWSSunder JJM Program under MMD PHE Dte. Sri Bikash Das, AE/Midnapur Mechanical Sub-Division-I Sri Bikas Pramanik, JE/Midnapur Mechanical Sub-Division,Sri Mahadev Dutta, JE/Midnapur Mechanical Sub-Division- ORD/000359/2023-2024 1687/W/MMD 04/08/2023 696 ORIENTAL ENGINEERING CO. 27.35 0.00 0 80
6 PASCHIM MEDINIPUR Kharagpur-II Midnapore Division RADHAKISHOR AND ITS ADJOINING MOUZAS PWSS , SM/18526 New Sinking of Tube Well, Laying distribution pipe line, Pump House, Boundary Wall, Soil investigation, 400 Cum OHR (Intze type with Pile foundation) & Accommodate FHTC (3,476 nos.) under JJM with allied work including 02 (Two ) Years Operation & Maintenance for Radhakishor & its adjoining mouzas PWSS in Kharagpur-II Block including supply of all labour & materials under Kharagpur Sub-Division of Midnapore Division, PHE Dte. in the District of Paschim Medinipur. AE Kharagpur Sub-division JE RWS Kharagpur Sub-Division(KGP-II) ORD/000348/2023-2024 4000/MD 06/10/2023 904 NATIONAL PROJECTS CONSTRUCTION CORPORATION LIMITED 1,051.83 277.39 26.37 70
Total 1,188.51 277.39 23.34