Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 549.93 169.63 30.85  
1 PASCHIM MEDINIPUR Kharagpur-II Midnapore Division CHAKKESHI AND ITS ADJOINING MOUZAS PWSS , SM/16259 New Material Requisition To Resource Division RTOR000090/2022-2023 198/MD 16/01/2023 0 Resource Division 26.69 0.00 0 0
2 PASCHIM MEDINIPUR Kharagpur-II Midnapore Division CHAKKESHI AND ITS ADJOINING MOUZAS PWSS , SM/16259 New Material Requisition To Resource Division RTOR000083/2024-2025 3434/MD 25/11/2024 0 Resource Division 11.38 0.00 0 0
3 PASCHIM MEDINIPUR Kharagpur-II Midnapore Mechanical CHAKKESHI AND ITS ADJOINING MOUZAS PWSS , SM/16259 New Quotation for new power connection at Chak keshi PWSS P/H- II , application no - 2004609056 , Ref id - 204222612 BILL/04188/2023-2024 BP-2023-24-772 06/03/2024 0 WBSEDCL 3.37 0.00 0 0
4 PASCHIM MEDINIPUR Kharagpur-II Midnapore Mechanical CHAKKESHI AND ITS ADJOINING MOUZAS PWSS , SM/16259 New Quotation for new power connection at ckakkesi PWSS , T/W - I , Application no - 2004582548 , Ref ID - 204206277 , Madpur CCC BILL/03750/2023-2024 BP-2023-24-707 16/02/2024 0 WBSEDCL 3.51 0.00 0 0
5 PASCHIM MEDINIPUR Kharagpur-II Midnapore Mechanical CHAKKESHI AND ITS ADJOINING MOUZAS PWSS , SM/16259 New Providing and Installation of Submersible pumping machineries and other electromechanical equipments for CHAKKESHI AND ITS ADJOINING MOUZAS PWSS under JJM Program under MMD PHE Dte. Sri Bikash Das, AE/Midnapur Mechanical Sub-Division-I Sri Mahadev Dutta, JE/Midnapur Mechanical Sub-Division-,Sri, Bikas Pramanik, JE, Estimator MMD ORD/001944/2022-2023 830/W/MMD 24/03/2023 739 WEST BENGAL ENGINEERING CO. 22.63 0.00 0 80
6 PASCHIM MEDINIPUR Kharagpur-II Midnapore Division CHAKKESHI AND ITS ADJOINING MOUZAS PWSS , SM/16259 New Sinking of Tube Well ,Laying distribution pipe line, Pump House , Boundary Wall, soil investigation , 200 Cum OHR (Intze type with Raft foundation) & Accommodate FHTC (1847 nos.) under JJM with allied work including 02(Two )Years Operation & Maintenance for Chakkeshi & its adjoining mouzas PWSS in Kharagpur-II Block including supply of all labour & materials under Kharagpur Sub-Division of Midnapore Division, PHE Dte. in the District of Paschim Medinipur. AE Kharagpur Sub-division JE RWS Kharagpur Sub-Division(KGP-II) ORD/000127/2023-2024 2525/MD 18/07/2023 893 SUJATA CONSTRUCTION 482.35 169.63 35.17 75
Total 549.94 169.63 30.84