Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 5,780.13 176.06 3.05  
1 PASCHIM MEDINIPUR Keshpur Midnapore Division KUBIR CHAK PIPED WATER SUPPLY SCHEME , SM/14484 New Material Requisition To Resource Division RTOR000050/2024-2025 3370/MD 25/11/2024 0 Resource Division 9.42 0.00 0 0
2 PASCHIM MEDINIPUR Keshpur Midnapore Mechanical KUBIR CHAK PIPED WATER SUPPLY SCHEME , SM/14484 New ELECTRIC QUOTATION BILL FOR TW NO-II of KUBIR CHAK PWSS. REF CONSUMER ID-204240650, APPLICATION NO-2004634372, APPLICATION TYPE-NEW CONNECTION, NAME OF CCC-UPPERKUAI CCC, NAME OF BLOCK-KESHPUR BILL/04478/2023-2024 BP-2023-24-848 14/03/2024 0 WBSEDCL 4.34 0.00 0 0
3 PASCHIM MEDINIPUR Keshpur Midnapore Mechanical KUBIR CHAK PIPED WATER SUPPLY SCHEME , SM/14484 New ELECTRIC QUOTATION BILL FOR TW NO-I of KUBIR CHAK PWSS. REF CONSUMER ID-204266459, APPLICATION NO-2004670480, APPLICATION TYPE-NEW CONNECTION, NAME OF CCC-UPPERKUAI CCC, NAME OF BLOCK-KESHPUR BILL/00290/2024-2025 BP-2024-25-46 18/04/2024 0 WBSEDCL 4.92 0.00 0 0
4 PASCHIM MEDINIPUR Keshpur Midnapore Mechanical KUBIR CHAK PIPED WATER SUPPLY SCHEME , SM/14484 New Providing and Installation of Submersible pumping machineries and other electromechanical equipments for KUBIR CHAK PIPED WATER SUPPLY SCHEME under JJM Program under MMD PHE Dte. Sri Bikash Das, AE/Midnapur Mechanical Sub-Division-I Sri Dablu Dutta, JE/Midnapur Mechanical Sub-Division-I ORD/001591/2022-2023 457/W/MMD 20/03/2023 805 KAMAKSHYA ENTERPRISE 22.77 17.63 77.43 25
5 PASCHIM MEDINIPUR Keshpur Midnapore Division KUBIR CHAK PIPED WATER SUPPLY SCHEME , SM/14484 New Construction of Different Capacity R.C.C. Over Head Reservoir Over Pile / Raft Foundation including Sub-Soil investigation works for Construction of Over Head Reservoir with Laying distribution system, Sinking of Tube Well, Pump House, Boundary Wall & Providing Functional Household Tap Connection (16,427 Nos.) for GAMARIA, UTTAR PIASHALA, KHAS JANGAL, ELUNI, GOPAL BANDH, JHETA JAMBONI, KUBIR CHAK & KUSUMDAHARI Pipe Water Supply Scheme within Keshpur Block under Midnapore Sadar Sub-Division of Midnapore Division PHE Dte. under Paschim Medinipur District. AE Sadar Sub-division JE RWS Sadar Sub-Division(Keshpur) ORD/000183/2023-2024 2735/MD 01/08/2023 890 M/S. S.S. ENTERPRISE 5,732.30 158.43 2.76 75
6 PASCHIM MEDINIPUR Keshpur Midnapore Division KUBIR CHAK PIPED WATER SUPPLY SCHEME , SM/14484 New Laying of rising main & interconnection for Kubir Chak & its adjoining mouzas PWSS, Block ¿ Keshpur, District ¿ Paschim Medinipur under Midnapore Division, PHE Dte. (Length = 400 Mtr.). AE Sadar Sub-division JE RWS Sadar Sub-Division(Keshpur) ORD/000383/2024-2025 58/MD 07/01/2025 45 MAHALAKSHMI ENTERPRISE 5.68 0.00 0 100
7 PASCHIM MEDINIPUR Keshpur Midnapore Mechanical KUBIR CHAK PIPED WATER SUPPLY SCHEME , SM/14484 New Making of T.W Foundation at PH-I of Kubirchak piped water supply scheme under MMD PHE Dte. Sri Bikash Das, AE/Midnapur Mechanical Sub-Division-I Sri Dablu Dutta, JE/Midnapur Mechanical Sub-Division-I ORD/000839/2025-2026 1128/MMSD-I 14/08/2025 7 KAMAKSHYA ENTERPRISE 0.70 0.00 0 0
Total 5,780.14 176.06 3.05