Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 5,784.67 243.35 4.21  
1 PASCHIM MEDINIPUR Keshpur Midnapore Mechanical UTTAR PIASHALA PIPED WATER SUPPLY SCHEME , SM/13810 New Providing and Installation of Submersible pumping machineries and other electromechanical equipments for UTTAR PIASHALA PIPED WATER SUPPLY SCHEME under JJM Program under MMD PHE Dte. Sri Bikash Das, AE/Midnapur Mechanical Sub-Division-I Sri Dablu Dutta, JE/Midnapur Mechanical Sub-Division-I ORD/001895/2022-2023 794/W/MMD 24/03/2023 180 PADMA ENGINEERING CO. 21.55 12.50 58 20
2 PASCHIM MEDINIPUR Keshpur Midnapore Division UTTAR PIASHALA PIPED WATER SUPPLY SCHEME , SM/13810 New Material Requisition To Resource Division RTOR000052/2024-2025 3372/MD 25/11/2024 0 Resource Division 14.24 0.00 0 0
3 PASCHIM MEDINIPUR Keshpur Midnapore Mechanical UTTAR PIASHALA PIPED WATER SUPPLY SCHEME , SM/13810 New ELECTRIC QUOTATION BILL FOR TW NO-I of UTTAR PIASALA PWSS. REF CONSUMER ID-204188705, APPLICATION NO-2004550684, APPLICATION TYPE-NEW CONNECTION, NAME OF CCC-UPPERKUAI CCC, NAME OF BLOCK-KESHPUR BILL/03732/2023-2024 BP-2023-24-693 16/02/2024 0 WBSEDCL 2.92 0.00 0 0
4 PASCHIM MEDINIPUR Keshpur Midnapore Mechanical UTTAR PIASHALA PIPED WATER SUPPLY SCHEME , SM/13810 New ELECTRIC QUOTATION BILL FOR TW NO-II of UTTAR PIASALA PWSS. REF CONSUMER ID-204200349, APPLICATION NO-2004571244 APPLICATION TYPE-NEW CONNECTION, NAME OF CCC-UPPERKUAI CCC, NAME OF BLOCK-KESHPUR BILL/03733/2023-2024 BP-2023-24-694 16/02/2024 0 WBSEDCL 4.26 0.00 0 0
5 PASCHIM MEDINIPUR Keshpur Midnapore Division UTTAR PIASHALA PIPED WATER SUPPLY SCHEME , SM/13810 New Construction of Different Capacity R.C.C. Over Head Reservoir Over Pile / Raft Foundation including Sub-Soil investigation works for Construction of Over Head Reservoir with Laying distribution system, Sinking of Tube Well, Pump House, Boundary Wall & Providing Functional Household Tap Connection (16,427 Nos.) for GAMARIA, UTTAR PIASHALA, KHAS JANGAL, ELUNI, GOPAL BANDH, JHETA JAMBONI, KUBIR CHAK & KUSUMDAHARI Pipe Water Supply Scheme within Keshpur Block under Midnapore Sadar Sub-Division of Midnapore Division PHE Dte. under Paschim Medinipur District. AE Sadar Sub-division JE RWS Sadar Sub-Division(Keshpur) ORD/000183/2023-2024 2735/MD 01/08/2023 890 M/S. S.S. ENTERPRISE 5,732.30 230.85 4.03 75
6 PASCHIM MEDINIPUR Keshpur Midnapore Division UTTAR PIASHALA PIPED WATER SUPPLY SCHEME , SM/13810 New Laying of rising main & interconnection for Uttar Piashala & its adjoining mouzas PWSS, Block: - Keshpur, District: - Paschim Midnapore under Midnapore Division, PHE Dte. (Length = 525 Mtr.) AE Sadar Sub-division JE RWS Sadar Sub-Division(Keshpur) ORD/000412/2024-2025 193/MD 17/01/2025 60 M/S. S.S. ENTERPRISE 5.74 0.00 0 0
7 PASCHIM MEDINIPUR Keshpur Midnapore Mechanical UTTAR PIASHALA PIPED WATER SUPPLY SCHEME , SM/13810 New Hiring of Inspection Vehicle (Diesel/CNG/LPG Driven) for supervision & monitoring of different ongoing piped water supply scheme for covering Midnapore Sadar Sub Division and its adjacent Sub -Division under JJM Programe for the office of Assistant Engineer, under M.M.S.D-I. P.H.E. Dte., Kharagpur , Inda. w.e.f.- w.e.f.-01-07-2025 to 28-02-2026 (Vehicle No. WB33C 6546) Sri Bikash Das, AE/Midnapur Mechanical Sub-Division-I Sri Lab Das, JE/Midnapur Mechanical Sub-Division-I ORD/000513/2025-2026 842/MMSD-I 11/06/2025 243 M/S BIKASH DE 3.66 0.00 0 0
Total 5,784.67 243.35 4.21