| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 21,711.33 | 121.07 | 0.56 | ||||||||||||||
| 1 | PASCHIM MEDINIPUR | Salbani | Midnapore Division | PATHRI AND AJOINING MOUJAS , SM/13807 | New | Material Requisition To Resource Division | RTOR000153/2022-2023 | 536/MD | 21/02/2023 | 0 | Resource Division | 9.38 | 0.00 | 0 | 0 | ||
| 2 | PASCHIM MEDINIPUR | Salbani | Midnapore Division | PATHRI AND AJOINING MOUJAS , SM/13807 | New | Sinking of 2 Nos. Tube well & Accommodate FHTC (100 Nos.) under JJM with allied work for Pathri PWSS in Salboni block including supply of all labour & materials within Midnapore Sadar Sub-Division under Midnapore Division, PHE Dte. [PART-A] | AE Sadar Sub-division | JE2 Sadar Sub-division | ORD/000110/2023-2024 | 2511/MD | 18/07/2023 | 45 | DEBASISH DOGRA | 21.94 | 15.55 | 70.88 | 70 |
| 3 | PASCHIM MEDINIPUR | Salbani | Midnapore Division | PATHRI AND AJOINING MOUJAS , SM/13807 | New | Laying distribution pipe line under JJM with allied work for Pathri PWSS in Salboni block including supply of all labour & materials within Midnapore Sadar Sub-Division under Midnapore Division, PHE Dte. [PART-E] | AE Sadar Sub-division | JE2 Sadar Sub-division | ORD/000103/2023-2024 | 2485/MD | 17/07/2023 | 521 | A R ENTERPRISE | 18.49 | 17.66 | 95.51 | 70 |
| 4 | PASCHIM MEDINIPUR | Salbani | Midnapore Division | PATHRI AND AJOINING MOUJAS , SM/13807 | New | Laying distribution pipe line & Accommodate FHTC (200 Nos.) under JJM with allied work for Pathri PWSS in Salboni block including supply of all labour & materials within Midnapore Sadar Sub-Division under Midnapore Division, PHE Dte. [PART-D] | AE Sadar Sub-division | JE2 Sadar Sub-division | ORD/000521/2023-2024 | 5500/MD | 14/12/2023 | 45 | MAHARAJA CONSTRUCTION CO. | 43.39 | 31.78 | 73.24 | 40 |
| 5 | PASCHIM MEDINIPUR | Salbani | Jhargram Mechanical Division | PATHRI AND AJOINING MOUJAS , SM/13807 | New | New Service connection charges for Pathri w/s scheme, t/w no.-II | BILL/01967/2023-2024 | 184/JMD | 30/03/2024 | 0 | WBSEDCL | 8.52 | 0.00 | 0 | 0 | ||
| 6 | PASCHIM MEDINIPUR | Salbani | Jhargram Mechanical Division | PATHRI AND AJOINING MOUJAS , SM/13807 | New | New Service connection charges for Pathri w/s scheme, t/w no.-I | BILL/01968/2023-2024 | 185/JMD | 30/03/2024 | 0 | WBSEDCL | 3.30 | 0.00 | 0 | 0 | ||
| 7 | PASCHIM MEDINIPUR | Salbani | Central Drilling | PATHRI AND AJOINING MOUJAS , SM/13807 | New | Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) | Assistant Engineer,Driller In Charge | Junior Engineer | ORD/000001/2023-2024 | 1415/CDD | 21/09/2023 | 304 | JHARGRAM SPV PRIVATE LIMITED | 21,339.76 | 13.03 | 0.06 | 11 |
| 8 | PASCHIM MEDINIPUR | Salbani | Midnapore Division | PATHRI AND AJOINING MOUJAS , SM/13807 | New | Laying distribution pipe line, Rising main & Accommodate FHTC (400 Nos.) including 2 yrs. O & M under JJM with allied work for Pathri PWSS in Salboni block including supply of all labour & materials within Midnapore Sadar Sub-Division under Midnapore Division, PHE Dte. [PART-C] | AE Sadar Sub-division | JE2 Sadar Sub-division | ORD/000148/2023-2024 | 2639/MD | 24/07/2023 | 723 | GOUTAM RAY | 138.15 | 43.05 | 31.16 | 70 |
| 9 | PASCHIM MEDINIPUR | Salbani | Midnapore Division | PATHRI AND AJOINING MOUJAS , SM/13807 | New | Construction of Pump House, Boundary wall & Accommodate FHTC (216 Nos.) under JJM with allied work for Pathri PWSS in Salboni block including supply of all labour & materials within Midnapore Sadar Sub-Division under Midnapore Division, PHE Dte. [PART-F] | AE Sadar Sub-division | JE2 Sadar Sub-division | ORD/000416/2023-2024 | 5152/MD | 07/11/2023 | 663 | BISWAS CONSTRUCTION | 45.23 | 0.00 | 0 | 81 |
| 10 | PASCHIM MEDINIPUR | Salbani | Midnapore Division | PATHRI AND AJOINING MOUJAS , SM/13807 | New | Construction of RCC OHR (150 CuM) & Accommodate FHTC (200 Nos.) under JJM with allied work for Pathri PWSS in Salboni block including supply of all labour & materials within Midnapore Sadar Sub-Division under Midnapore Division, PHE Dte. [PART-B] | AE Sadar Sub-division | ORD/000547/2024-2025 | 738/MD | 19/03/2025 | 180 | SAMIT PAL | 83.17 | 0.00 | 0 | 0 | |
| Total | 21,711.32 | 121.06 | 0.56 | ||||||||||||||