Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 431.78 155.31 35.97  
1 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Based Pipe Water Supply Scheme for Maligram & its adj. mouzas, Block - Pingla, Dist.- Paschim Medinipur. , SM/13123 Augmentation Material Requisition To Resource Division RTOR000168/2023-2024 1368/MD 02/05/2023 0 Resource Division 38.07 0.00 0 0
2 PASCHIM MEDINIPUR Midnapore Mechanical Augmentation of Ground Based Pipe Water Supply Scheme for Maligram & its adj. mouzas, Block - Pingla, Dist.- Paschim Medinipur. , SM/13123 Augmentation Quotation for Addl. TW-IV of Maligram W/S Scheme (Consumer ID 203971943) BILL/00076/2023-2024 BP-2023-24-35 04/05/2023 0 WBSEDCL 4.08 0.00 0 0
3 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Based Pipe Water Supply Scheme for Maligram & its adj. mouzas, Block - Pingla, Dist.- Paschim Medinipur. , SM/13123 Augmentation Additional work in connection of Laying of Distribution pipe line for Augmentation of Maligram Pipe Water Supply Scheme under Pingla Block within Midnapore Division, PHE Dte. AE Kharagpur Sub-division ORD/000311/2024-2025 3404/MD 25/11/2024 90 UTTAM KUMAR DAS 80.70 0.00 0 0
4 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Based Pipe Water Supply Scheme for Maligram & its adj. mouzas, Block - Pingla, Dist.- Paschim Medinipur. , SM/13123 Augmentation Preparation of D.P.R (Consultancy work) in connection with the Functional House Hold Connection for Rejuvination / Augmentation of existing Maligram PWSS Within Pingla Block under Midnapore Division P.H.E. Dte AE Kharagpur Sub-division ORD/000272/2022-2023 547/AE/KSD 23/08/2022 30 GOBINDA MAITY 3.06 3.00 98.04 100
5 PASCHIM MEDINIPUR Midnapore Mechanical Augmentation of Ground Based Pipe Water Supply Scheme for Maligram & its adj. mouzas, Block - Pingla, Dist.- Paschim Medinipur. , SM/13123 Augmentation Providing and Installation of Submersible pumping machineries and other electromechanical equipments for Augmentation of Ground Based Pipe Water Supply Scheme for Maligram & its adj. mouzas, Block - Pingla, Dist.- Paschim Medinipur. under JJM Program under MMD PHE Dte. Sri Bikash Das, AE/Midnapur Mechanical Sub-Division-I Sri Dablu Dutta, JE/Midnapur Mechanical Sub-Division-I ORD/001607/2022-2023 487/W/MMD 20/03/2023 1032 M/S MANABESH ROY 22.93 10.66 46.49 40
6 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Based Pipe Water Supply Scheme for Maligram & its adj. mouzas, Block - Pingla, Dist.- Paschim Medinipur. , SM/13123 Augmentation Sinking of Tube Well, Laying distribution pipe line, Pump House, Boundary wall for Augmentation of Maligram PWSS in Pingla block including supply of all labour & materials within Kharagpur Sub-Division under Midnapore Division, PHE Dte. AE Kharagpur Sub-division JE1 Kharagpur Sub-division ORD/000586/2022-2023 297/MD 24/01/2023 813 M/S. D.K.H.CONSTRUCTION 282.94 141.65 50.06 61
Total 431.77 155.31 35.97