Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
13 402.16 110.4 27.45  
1 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Sinking of Rig bored 250mm x 150mm dia. & 300 mtr. Deep Tubewell by Rotary method for ALIPOREPIPE WATER SUPPLY SCHEME in the Arsenic affected areas of South 24 Pgs. Dist. in BISHNUPUR-I Block under South 24 Pgs W/S Sub-Division-II, P.H.E. Dte. AE SWSD-II JE2 ORD/000031/2022-2023 915/SWD-I 19/07/2022 30 SIMPLEX DRILLING CO. 14.18 13.06 92.1 100
2 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Preparation and submission of Detailed Project Report of "ALIPUR Ground Water Based Piped Water Supply Scheme" in BISHNUPUR-I block under Surface Water Based Water Supply Scheme in the Arsenic affected areas of South 24-Pgns. district. AE SWSD-II ORD/000400/2022-2023 458/SWD-I 24/05/2022 15 GEO SOLUTION 2.51 2.50 99.6 100
3 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Material Requisition To Resource Division RTOR000116/2022-2023 3249/SWD-I 01/03/2023 Resource Division 32.09 0.00 0 0
4 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Additional work for sinking of Rig bored 250 mm x 150 mm dia. & 300 mtr. deep Tube well to achieve 66 mtr. housing pipe by Rotary Method for ALIPORE PWSS of Bishnupur-I Block for Augmentation of Surface Water Based W/S Scheme in the Arsenic Affected Areas of South 24-Parganas district under South 24-Parganas W/S Division- I, P.H.E. Dte. [TSM/011230] AE SWSD-II JE2 ORD/000507/2022-2023 2905/SWD-I 14/02/2023 15 SIMPLEX DRILLING COMPANY 1.59 1.59 100 100
5 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Development of low land and temporary aproach road for entering Tubewell site for proposed ALIPORE Piped Water Supply Scheme in Bishnupur-I Block for Augmentation of Surface Water Based Water Supply Scheme in the Arsenic Affected Areas of South 24 Pgs. Dist. under South 24 Pgs. Water Supply Division-I, PHE Dte. [TSM/011230] AE SWSD-II JE2 ORD/000811/2022-2023 3703/SWD-I 30/03/2023 15 SIMPLEX DRILLING COMPANY 0.88 0.75 85.23 100
6 SOUTH 24 PARAGANAS Bishnupur - I S24 Pgns Mechanical Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1&2, of Alipore water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Bishnupur-I] Assistant Engineer -II Junior Engineer ORD/000468/2022-2023 279/SMD 01/02/2023 90 NITESH MANAGEMENT 26.52 0.00 0 0
7 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Land Development at 1st Tubewell site under Alipore PWSS to accommodate FHTC in Bishnupur-I Block under South 24 pgs W/S Division-I, P.H.E Dte. [TSM/011230] AE SWSD-II ORD/000245/2023-2024 1487/SWD-I 19/07/2023 15 MAA LAXMI ENTERPRISE 2.97 2.97 100 100
8 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Material Requisition To Resource Division RTOR000014/2022-2023 1583/SWD-I 17/10/2022 Resource Division 6.39 0.00 0 0
9 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Construction of (Size 4.80mX3.66m) Pump House with water supply and sanitary arrangement (as per Deptt. drawing) of ALIPUR Pipe Water Supply Scheme in Bishnupur-I block under South 24-Pgns W/S Divn-I, PHE Dte. (SM/11493) (3rd Call) AE SWSD-II JE2 ORD/000251/2023-2024 1498/SWD-I 20/07/2023 60 RAMASISH ENTERPRISE 5.91 0.00 0 1
10 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Sinking of Rig bored 250mm x 150mm dia. & 300 mtr. deepTubewell having 66 mtr. housing pipe by Rotary method at Second Tubewell site for ALIPORE PWSS of BISHNUPUR-I block for Augmentaion of Surface Water Based W/S Scheme in the Arsenic Affected Areas of South 24 Pgs district under South 24-Parganas W/S Division-I, P.H.E. Dte. [TSM/011230] AE SWSD-II JE2 ORD/000597/2022-2023 3124/SWD-I 24/02/2023 30 CIVIL CONSULTANT 15.88 0.00 0 0
11 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Laying Distribution System with providing Functional Household Tap Connection (FHTC) for Proposed ALIPORE PIPE WATER SUPPLY SCHEME Arsenic affected areas of South 24-Pgs. Dist. in BISHNUPUR-I Block under South 24 Pgs W/S Sub-Division -II, P.H.E. Dte. [No. of FHTC = 1038] AE SWSD-II JE2 ORD/000184/2022-2023 1487/SWD-I 28/09/2022 90 MAA LAXMI ENTERPRISE 119.84 85.88 71.66 90
12 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Construction of Boundary Wall & other allied works at 12 (twelve) nos. Head Work Sites of different PWSS within Bishnupur-I Block, Dist.-South 24-Parganas for Augmentation of Surface Water based Water Supply Scheme in the Arsenic Affected areas of South 24-Parganas District. AE SWSD-II JE1,JE2,JE4 ORD/000209/2023-2024 1377/SWD-I 12/07/2023 150 CONCORD PROJECTS PVT. LTD. 105.47 3.65 3.46 15
13 SOUTH 24 PARAGANAS Bishnupur - I South 24 Pgs W/S Division I Proposed ground water based ALIPORE piped water supply scheme to accommodate FHTC in BISHNUPUR-I Block under South 24 pgns W/S Division-I, South 24 Parganas District. , SM/11493 New Laying rising main & additional pipeline for distribution system, construction of boundary walls for 1st & 2nd Tubewell sites and other allied works for proposed ground water based ALIPORE PWSS to accommodate FHTC in Bishnupur - I Block under South 24 parganas W/S Divn-I, PHE Dte. South 24 Pgns District. (SM/11493) ORD/000274/2024-2025 2924/SWD-I 25/06/2024 45 MAA LAXMI ENTERPRISE 67.93 0.00 0 0
Total 402.17 110.41 27.45