| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 4 | 83.63 | 0 | 0 | ||||||||||||||
| 1 | Alipore Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR SABEK MAHISAHARA AND ADJOINING MOUZA (CHUNPURI) , | Construction of 1 (one) no. switch room cum chlorine room (4.88m x 3.66m) including Sanitary arrangement as per departmental drawing at the site for the Augmentation of Sabek Mahisahara & Adjoining Mouzas (Chunpuri) W/S Scheme, Block - Canning-II under Canning Sub-Division of Alipore Division, PHE Dte. [ Pump House No. - I] (3rd Call) | Assistant Engineer, Canning sub division | Junior Engineer, 4 CSD,Junior Engineer,1 CSD | ORD/000538/2024-2025 | 3709/AD | 12/09/2024 | 45 | NIJAMUDDIN ENTERPRISE | 6.97 | 0.00 | 0 | 0 | |||
| 2 | Alipore Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR SABEK MAHISAHARA AND ADJOINING MOUZA (CHUNPURI) , | Sinking of 01 (one) no. 250mm x 150mm dia. 300 mtr. deep Tubewell by Direct Rotary Rig Method using P.V.C pipe and pre-packed Resin Bonded Gravel Filter for the Augmentation of Sabek Mahisahara & Adjoining Mouzas (Chunpuri) W/S Scheme, Block - Canning-II under Canning Sub Division of Alipore Division, PHE Dte. (TW. No. 1) | Assistant Engineer, Canning sub division | Junior Engineer, 4 CSD | ORD/002376/2023-2024 | 1200/AD | 29/02/2024 | 450 | PADMA ENGINEERING CO | 17.31 | 0.00 | 0 | 0 | |||
| 3 | Alipore Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR SABEK MAHISAHARA AND ADJOINING MOUZA (CHUNPURI) , | Laying distribution system with supply of specials for Augmentation of Ground Water Based Piped Water Supply Scheme for Sabek Mahisahara and Adjoining Mouzas (Chunpuri), Block - Canning-II under Canning Sub-Division of Alipore Division, P.H.E. Dte. | Assistant Engineer, Canning sub division | Junior Engineer, 4 CSD | ORD/000279/2024-2025 | 2494/AD | 14/06/2024 | 353 | TARUN KUMAR LAHA | 48.15 | 0.00 | 0 | 15 | |||
| 4 | S24 Pgns Mechanical | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR SABEK MAHISAHARA AND ADJOINING MOUZA (CHUNPURI) , | Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1 for Augmentation of Sabek Mahisahara water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Canning-II] (SM/18863) | Assistant Engineer | Junior Engineer | ORD/000100/2025-2026 | 1179/SMD | 28/04/2025 | 135 | PS & ASSOCIATES | 11.20 | 0.00 | 0 | 0 | |||
| Total | 83.64 | 0.00 | 0 | ||||||||||||||