Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 44.37 26.16 58.96  
1 SOUTH 24 PARGANAS Canning-II S24 Pgns Mechanical Ground Water Based Mini Piped Water Supply Scheme (maximum 100 nos. households) of KULER KHOJ village of Tambuldaha-II Gram Panchayet in Canning-II Block considering 1 no Tubewell (150 mm x 100 mm x 300 m depth), PVC Tank 15000 Lit, 1.2 km distribution sy , SM/12576 New Quotation for new service( power) connection at Kuler khoj PH-1 Water supply scheme under Canning-II block. Reference ID:-106599046, Application No :-1007775984 BILL/01847/2024-2025 29/10/2024 0 WBSEDCL 10.53 0.00 0 0
2 SOUTH 24 PARGANAS Canning-II Alipore Division Ground Water Based Mini Piped Water Supply Scheme (maximum 100 nos. households) of KULER KHOJ village of Tambuldaha-II Gram Panchayet in Canning-II Block considering 1 no Tubewell (150 mm x 100 mm x 300 m depth), PVC Tank 15000 Lit, 1.2 km distribution sy , SM/12576 New Sinking of 150 X 100 mm dia. X 300 Mtr. Depth Rig bored Tube wells, Construction of  Switch Room (3750 X 3750), Pipe connections, Laying of delivery main & Laying of Distribution System, Providing Functional Household Tap Connection, &Supplying and installation PVC storage tank etc. of Ground Water Based Mini Piped Water Supply Scheme for the Kuler Khonj having village with maximum 85 nos. households, Block - Canning -II under Canning Sub Division of Alipore Division, PHE Dte. Assistant Engineer, Canning sub division Junior Engineer, 2 CSD ORD/000766/2022-2023 6495/AD 11/11/2022 60 SURYA ENTERPRISE 33.84 26.16 77.3 88
Total 44.38 26.16 58.94