Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
3 22.45 0 0  
1 Alipore Division Retrofitting for Providing FHTC at Ground Water Based Haradhanpur Water Supply Scheme, Block : Sagar, District- South 24 Pgs. (Phase-A) , Preparation of DPR including estimate for Providing FHTC at Companirchar W/S Scheme (Phase-A), Haradhanpur W/S Scheme (Phase-A) & Krishnanagar W/S Scheme (Phase-A) W/S Scheme & it's adjacent areas, Block - Sagar under Kakdwip Sub - Division of Alipore Division, P.H.E. Dte. [W/O No. 519/KSD, 24.8.21, T.No. 1784/AD, 21-22] VCH/002604/2021-2022 BP-2021-22-507 22/03/2022 0 LEMNISCATE 3.53 0.00 0 0
2 Alipore Division Retrofitting for Providing FHTC at Ground Water Based Haradhanpur Water Supply Scheme, Block : Sagar, District- South 24 Pgs. (Phase-A) , Material Requisition To Resource Division RTOR000697/2023-2024 467/AD 24/01/2024 0 Resource Division 10.80 0.00 0 0
3 Alipore Division Retrofitting for Providing FHTC at Ground Water Based Haradhanpur Water Supply Scheme, Block : Sagar, District- South 24 Pgs. (Phase-A) , Repairing of 1 no. Pump House, Earth Filling, Boundary Wall Painting and Repair, Approach Road at 1st Tubewell site for Haradhanpur (Zone-I) Water Supply Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (SM/14159) (SM/09393) (SM/08793) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/000450/2025-2026 3568/AD 25/07/2025 45 PALASH HALDAR 8.12 0.00 0 0
Total 22.44 0.00 0