Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 242.78 0 0  
1 Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 06 (six) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Goran Bose Water Supply Sc , Construction of boundary wall at Pump House No. - 2 at Ground Water Based Augmentation Piped Water Supply Scheme of Goranbose W/S Scheme Block - Basanti under Canning Sub-Division of Alipore Division, PHE Dte. Assistant Engineer, Canning sub division Junior Engineer,1 CSD ORD/000748/2024-2025 4420/AD 05/11/2024 30 MODERN CONSTRUCTION 20.83 0.00 0 0
2 Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 06 (six) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Goran Bose Water Supply Sc , Construction of boundary wall at Pump House No. - 1 at Ground Water Based Augmentation Piped Water Supply Scheme of Goranbose W/S Scheme Block - Basanti under Canning Sub-Division of Alipore Division, PHE Dte. Assistant Engineer, Canning sub division Junior Engineer,1 CSD ORD/000747/2024-2025 4419/AD 05/11/2024 30 S.S. CONSTRUCTION 29.61 0.00 0 0
3 Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 06 (six) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Goran Bose Water Supply Sc , Material Requisition To Resource Division RTOR000399/2023-2024 357/AD 19/01/2024 0 Resource Division 3.82 0.00 0 0
4 Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 06 (six) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Goran Bose Water Supply Sc , Construction of 600 m³ capacity R.C.C OHR (based on Departmental Design &. Drawing) with 20 mtr. staging height including foundation, pipeline connection and cost of pipes , specials etc. of Goranbose piped water supply scheme of Basanti Block under Canning Sub- Division of Alipore Division, PHE Dte. (SM/05716) Assistant Engineer, Canning sub division Junior Engineer,1 CSD ORD/002095/2024-2025 351/AD 28/01/2025 300 MS SINHA ROY & CO 181.43 0.00 0 0
5 Alipore Division Retrofitting of distribution system for Providing Functional Household Tap Connection (FHTC) to all the households for 06 (six) nos. habitation of all the households in connection with Jal Jeevan Mission (JJM) and Jal Swapna for Goran Bose Water Supply Sc , Construction of switch room cum chlorine room (4.88m x 3.66m) including Sanitary arrangement as per departmental drawing at the site of Augmentation of Goranbose W/S Scheme, Block-Basanti under Canning Sub-Division of Alipore Division, PHE Dte. (PH - 4) Assistant Engineer, Canning sub division Junior Engineer,1 CSD ORD/001711/2022-2023 11675/AD 20/02/2023 720 A 8 T CONSTRUCTION 7.09 0.00 0 100
Total 242.79 0.00 0