| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 3 | 1,364.28 | 0 | 0 | ||||||||||||||
| 1 | HOWRAH | Tamluk Division | Engagement of Implementation Support Agency (ISA) for implementation of community mobilization & capacity building activities at Jhargram , Purba Medinipur, Howrah districts Under Jal Jeevan Mission (JJM) Support Activities , SM/19354 | Continuation Work Order for Engagement of Implementation Support Agency (ISA) for implementation of community mobilization & capacity building support activities at Purba Medinipore district Under Jal Jeevan Mission (JJM) under Tamluk Division, PHE Dte. (i.e. 03.04.2025 to 02.04.2026. For 12 months) | Assistant Engineer | Junior Engineer | ORD/000658/2024-2025 | 943/TD | 27/03/2025 | 365 | HARISHCHANDRAPUR PALLY UNNAYAN SAMITY | 454.76 | 0.00 | 0 | 50 | ||
| 2 | JHARGRAM | Tamluk Division | Engagement of Implementation Support Agency (ISA) for implementation of community mobilization & capacity building activities at Jhargram , Purba Medinipur, Howrah districts Under Jal Jeevan Mission (JJM) Support Activities , SM/19354 | Continuation Work Order for Engagement of Implementation Support Agency (ISA) for implementation of community mobilization & capacity building support activities at Purba Medinipore district Under Jal Jeevan Mission (JJM) under Tamluk Division, PHE Dte. (i.e. 03.04.2025 to 02.04.2026. For 12 months) | Assistant Engineer | Junior Engineer | ORD/000658/2024-2025 | 943/TD | 27/03/2025 | 365 | HARISHCHANDRAPUR PALLY UNNAYAN SAMITY | 454.76 | 0.00 | 0 | 50 | ||
| 3 | PURBA MEDINIPUR | Tamluk Division | Engagement of Implementation Support Agency (ISA) for implementation of community mobilization & capacity building activities at Jhargram , Purba Medinipur, Howrah districts Under Jal Jeevan Mission (JJM) Support Activities , SM/19354 | Continuation Work Order for Engagement of Implementation Support Agency (ISA) for implementation of community mobilization & capacity building support activities at Purba Medinipore district Under Jal Jeevan Mission (JJM) under Tamluk Division, PHE Dte. (i.e. 03.04.2025 to 02.04.2026. For 12 months) | Assistant Engineer | Junior Engineer | ORD/000658/2024-2025 | 943/TD | 27/03/2025 | 365 | HARISHCHANDRAPUR PALLY UNNAYAN SAMITY | 454.76 | 0.00 | 0 | 50 | ||
| Total | 1,364.27 | 0.00 | 0 | ||||||||||||||