Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 25.61 10.89 42.52  
1 BANKURA Bankura Mechanical Construction of Grid-Connected solar photo -voltaic system for Ekteswar PWSS scheme Dist Bankura , SM/15312 Acceptance cum Formal work order for the work of Construction of Grid-connected Solar Photo-voltaic System for Ekteswar PWS Scheme under Bankura Mechanical Division PHE Dte. Dist: Bankura Assistant Engineer Junior Engineer ORD/000473/2022-2023 480/BMD 23/03/2023 60 GOENKA ENTERPRISE 25.01 10.89 43.54 88
2 BANKURA Bankura Mechanical Construction of Grid-Connected solar photo -voltaic system for Ekteswar PWSS scheme Dist Bankura , SM/15312 New NET meter connection for on grid solar system at EKTESHWAR water supply scheme at mouza-Sankarhati under BMD PHE Dte. BILL/00300/2024-2025 BP-2024-25-67 24/07/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 0.60 0.00 0 null
Total 25.61 10.89 42.54