| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 7 | 1,147.94 | 304.81 | 26.55 | ||||||||||||||
| 1 | BANKURA | Kotulpur | Bankura Division | Panahar Piped Water Supply Scheme , SM/18790 | New | Material Requisition To Resource Division | RTOR000024/2023-2024 | 1120/BQA | 12/05/2023 | 0 | Resource Division | 111.45 | 0.00 | 0 | 0 | ||
| 2 | BANKURA | Kotulpur | Bankura Mechanical | Panahar Piped Water Supply Scheme , SM/18790 | New | Acceptance cum Formal work order for the work of Providing, installation of Pumping machineries with other electro-mechanical accessories for newly sunk TW No-I, TW No-II & TW No-III of Panahar piped water supply scheme under Bankura Mechanical Division, PHE Dte. Block : Kotulpur , Dist: Bankura. | Assistant Engineer | Junior Engineer | ORD/000167/2023-2024 | 2065/BMD | 11/09/2023 | 180 | PROGRESSIVE ENGINEERS CO-OPERATIVE SOCIETY LIMITED | 59.03 | 27.30 | 46.25 | 46 |
| 3 | BANKURA | Kotulpur | Bankura Mechanical | Panahar Piped Water Supply Scheme , SM/18790 | New | New service connection connection at P/H no-I of panahar W/S scheme. | BILL/00528/2024-2025 | BP-2024-25-137 | 25/07/2024 | 0 | WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. | 3.80 | 0.00 | 0 | 0 | ||
| 4 | BANKURA | Kotulpur | Bankura Mechanical | Panahar Piped Water Supply Scheme , SM/18790 | New | New service connection at P/H-III of Panahar W/S scheme | BILL/00529/2024-2025 | BP-2024-25-138 | 25/07/2024 | 0 | WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. | 7.99 | 0.00 | 0 | 0 | ||
| 5 | BANKURA | Kotulpur | Bankura Mechanical | Panahar Piped Water Supply Scheme , SM/18790 | New | New service connection at P/H-III of Panahar W/S scheme | BILL/00527/2024-2025 | BP-2024-25-136 | 25/07/2024 | 0 | WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. | 8.18 | 0.00 | 0 | 0 | ||
| 6 | BANKURA | Kotulpur | Bankura Division | Panahar Piped Water Supply Scheme , SM/18790 | New | SUPPLY, DELIVERY, CONSTRUCTION, COMMISSIONING AND COMPLETION OF ALL CIVIL WORKS INCLUDING ALL ALLIED, RELATED AND ENABLING WORKS FOR PANHAR PIPED WATER SUPPLY SCHEME, BLOCK- KOTULPUR, DIST- BANKURA UNDER JJM INCLUDING TRIAL RUN FOR 3 MONTHS AND O&M FOR A PERIOD OF 3 YEARS UNDER BANKURA DIVISION,PHE Dte. | Assistant Engineer | Junior Engineer | ORD/000754/2023-2024 | 2742/BQA | 04/10/2023 | 820 | GOPAL CHANDRA CHOWDHURY | 806.18 | 277.51 | 34.42 | 85 |
| 7 | BANKURA | Kotulpur | Bankura Division | Panahar Piped Water Supply Scheme , SM/18790 | New | Balanced ancillary works for Panahar Water Supply Scheme under Kotulpur Block under Bishnupur Sub-Division of Bankura Division, P.H.E. Dte. (SM/18790) | Assistant Engineer | Junior Engineer | ORD/001946/2024-2025 | 692/BQA | 12/03/2025 | 295 | GOPAL CHANDRA CHOWDHURY | 151.31 | 0.00 | 0 | 85 |
| Total | 1,147.93 | 304.81 | 26.55 | ||||||||||||||