Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 13,821.23 193.75 1.4  
1 BANKURA Patrasayer Bankura Division Goala Danga Piped Water Supply Scheme. , SM/14001 New Material Requisition To Resource Division RTOR000048/2023-2024 1120/BQA 12/05/2023 0 Resource Division 14.56 0.00 0 0
2 BANKURA Patrasayer Bankura Division Goala Danga Piped Water Supply Scheme. , SM/14001 New Material Requisition To Resource Division RTOR000017/2024-2025 2945/BQA 21/11/2024 0 Resource Division 8.46 0.00 0 0
3 BANKURA Patrasayer Bankura Division Goala Danga Piped Water Supply Scheme. , SM/14001 New Material Requisition To Resource Division RTOR000007/2024-2025 2011/BQA 26/07/2024 0 Resource Division 4.39 0.00 0 0
4 BANKURA Patrasayer Bankura Mechanical Goala Danga Piped Water Supply Scheme. , SM/14001 New New service connection for GOALA DANGA water supply scheme under Bankura Mechanical Division PHE Dte BILL/00016/2024-2025 BP-2024-25-32 10/05/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 9.63 0.00 0 0
5 BANKURA Patrasayer Bankura Mechanical Goala Danga Piped Water Supply Scheme. , SM/14001 New Goala Danga Piped Water Supply Scheme. BILL/01614/2023-2024 BP-2023-24-142 07/03/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 3.78 0.00 0 0
6 BANKURA Patrasayer Bankura Division Goala Danga Piped Water Supply Scheme. , SM/14001 New SUPPLY, DELIVERY, CONSTRUCTION, COMMISSIONING AND COMPLETION OF ALL CIVIL & ELECTRO MECHANICAL WORKS INCLUDING ALL ALLIED, RELATED AND ENABLING WORKS FOR PATSOL, RAUTARA, BRINDABANPUR, TELRUI, RANPUR, NANDAMOHANPUR & NARUALA PIPED WATER SUPPLY SCHEME OF SONAMUKHI BLOCK , DHULA DANGA, LEGO, NARAYANPUR, PRATAPPUR, NANDAGRAM, LANKAJOL & DESHRA PIPED WATER SUPPLY SCHEME OF KOTULPUR BLOCK AND BINOD NAGAR, JAMKURI, GOALA, KUSHADWIP, MUKUNDAPUR & NANDUR PIPED WATER SUPPLY SCHEME OF PATRASAYER BLOCK, DIST- BANKURA UNDER JJM INCLUDING TRIAL RUN FOR 3 MONTHS AND O&M FOR A PERIOD OF 3 YEARS UNDER BANKURA DIVISION,PHE Dte. Assistant Engineer Junior Engineer ORD/000356/2023-2024 2024/BQA 24/07/2023 526 MACKINTOSH BURN LIMITED 13,769.53 193.75 1.41 55
7 BANKURA Patrasayer Bankura Mechanical Goala Danga Piped Water Supply Scheme. , SM/14001 New Acceptance cum Formal work order for the work of Providing and installation of Electromagnetic flowmeter with motorized Sluice Valve for respective OHR for at Goala Danga Piped Water Supply Scheme under BMD PHE Dte Dist-Bankura. Assistant Engineer Junior Engineer ORD/000022/2025-2026 233/BMD 14/05/2025 90 M/S BIPUL BANERJEE 10.88 0.00 0 0
Total 13,821.22 193.75 1.4