Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
3 2.35 0 0  
1 HOOGHLY Hooghly Division Retrofitting work for Providing Functional Household Tap Connection (FHTC) within the uncovered portion of Chopa Water Supply Scheme under Dhaniakhali Block , SM/18108 Retrofitting 2nd Continuation of Maintenance of Laying Distribution System including Street Stand post, Rising main & other essential components of Chopa, Gopinagar, Dantra, Hassampore, Dighir W/S Scheme for the period from 01/07/2023 to 31/07 /2023 under Chinsurah Sub-Division P.H.E.Dte. Assistant Engineer (Civil) ORD/000234/2023-2024 562/CH 27/06/2023 31 BOSE ENTERPRISE (RATUL BOSE) 0.79 0.00 0 0
2 HOOGHLY Hooghly Division Retrofitting work for Providing Functional Household Tap Connection (FHTC) within the uncovered portion of Chopa Water Supply Scheme under Dhaniakhali Block , SM/18108 Retrofitting 1st Continuation of Maintenance of Laying Distribution System including Street Stand post, Rising main & other essential components of Chopa, Gopinagar, Dantra, Hassampore, Dighir W/S Scheme for the period from 01/06/2023 to 30/06 /2023 under Chinsurah Sub-Division P.H.E.Dte. Assistant Engineer (Civil) Junior Engineer (Civill) ORD/000233/2023-2024 459/CH 29/05/2023 30 BOSE ENTERPRISE (RATUL BOSE) 0.77 0.00 0 0
3 HOOGHLY Hooghly Division Retrofitting work for Providing Functional Household Tap Connection (FHTC) within the uncovered portion of Chopa Water Supply Scheme under Dhaniakhali Block , SM/18108 Retrofitting 3RD Continuation of Maintenance of Laying Distribution System including Street Stand post, Rising main & other essential components of Chopa, Gopinagar, Dantra, Hassampore, Dighir W/S Scheme for the period from 01/08/2023 to 31/08 /2023 under Chinsurah Sub-Division P.H.E.Dte. Assistant Engineer (Civil) ORD/000575/2023-2024 713/CH 28/07/2023 31 BOSE ENTERPRISE (RATUL BOSE) 0.79 0.00 0 0
Total 2.35 0.00 0