Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 434.06 68.3 15.74  
1 HOOGHLY Haripal Hooghly Division Mahishtikri (Zone-I) Piped Water Supply Scheme, Block- Haripal, District-Hooghly , SM/16979 New Material Requisition To Resource Division RTOR000074/2023-2024 1235/12/Hug 28/04/2023 Resource Division 58.83 0.00 0 0
2 HOOGHLY Haripal Hooghly Division Mahishtikri (Zone-I) Piped Water Supply Scheme, Block- Haripal, District-Hooghly , SM/16979 New Material Requisition To Resource Division RTOR000274/2023-2024 1383/25/Hug 15/05/2023 Resource Division 5.09 0.00 0 0
3 HOOGHLY Haripal Electrical Mahishtikri (Zone-I) Piped Water Supply Scheme, Block- Haripal, District-Hooghly , SM/16979 New Adhoc payment to WBSEDCL against Service Connection BILL/01125/2023-2024 null 28/06/2023 WBSEDCL 71.17 0.00 0 0
4 HOOGHLY Haripal Hooghly Division Mahishtikri (Zone-I) Piped Water Supply Scheme, Block- Haripal, District-Hooghly , SM/16979 New Material Requisition To Resource Division RTOR000440/2023-2024 3058/15/Hug 11/10/2023 Resource Division 5.09 0.00 0 0
5 HOOGHLY Haripal Electrical Mahishtikri (Zone-I) Piped Water Supply Scheme, Block- Haripal, District-Hooghly , SM/16979 New Quotation Bill for New Service Connection at Mahishtikri W/S. Sch. TW-I, Z-I BILL/04168/2023-2024 407 09/11/2023 WBSEDCL 3.04 0.00 0 0
6 HOOGHLY Haripal Electrical Mahishtikri (Zone-I) Piped Water Supply Scheme, Block- Haripal, District-Hooghly , SM/16979 New Quotation Bill for New Service Connection at Mahishtikari W/S. Sch. TW-II, Z-I BILL/04167/2023-2024 406 09/11/2023 WBSEDCL 3.91 0.00 0 0
7 HOOGHLY Haripal Electrical Mahishtikri (Zone-I) Piped Water Supply Scheme, Block- Haripal, District-Hooghly , SM/16979 New Supply, delivery & installation of submersible pumping machinery and other electrical/ mechanical equipments etc. including allied works for Mahishtikri (Zone-I) water supply scheme, T.W. No. I & II, Block: Haripal, District- Hooghly under Electrical Division, PHE Dte. Assistant Engineer 2 Junior Engineer4 ORD/000042/2023-2024 1728/ED 19/04/2023 90 MENAKA ENTERPRISE 20.26 9.73 48.03 30
8 HOOGHLY Haripal Hooghly Division Mahishtikri (Zone-I) Piped Water Supply Scheme, Block- Haripal, District-Hooghly , SM/16979 New MAHISHTIKRI ZONE-I Piped Water Supply Scheme with Sinking of tube-well, LDS, Rising Main, FHTC & construction of switch-rooms & boundary walls at different TW site under HARIPAL Block, District:- Hooghly [NEW SCHEME] Assistant Engineer (Civil) Haripal Block junior Enginner ORD/000195/2023-2024 1786/HUG 16/06/2023 90 MAA TARA CONSTRUCTION 266.67 58.57 21.96 25
Total 434.05 68.30 15.74