Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 3,512.64 78.37 2.23  
1 HOOGHLY Chanditala - I Electrical NABABPUR PIPED WATER SUPPLY SCHEME BLOCK- CHANDITALA-I, DISTRICT: HOOGHLY , SM/12239 New Supply, delivery & installation of submersible pumping machinery and other electrical/ mechanical equipments etc. including allied works for Nababpur water supply scheme, T.W. No.- I & II, Block: Chanditala-I, District- Hooghly under Electrical Division, PHE Dte. Assistant Engineer Howrah mechanical Sub Division Junior Engineer2 ORD/000164/2022-2023 3498/ED 30/12/2022 90 ANJAN ENTERPRISE 21.33 0.00 0 0
2 HOOGHLY Chanditala - I Electrical NABABPUR PIPED WATER SUPPLY SCHEME BLOCK- CHANDITALA-I, DISTRICT: HOOGHLY , SM/12239 New Adhoc payment to WBSEDCL against service connnection. BILL/01121/2023-2024 null 28/06/2023 WBSEDCL 97.65 0.00 0 0
3 HOOGHLY Chanditala - I Electrical NABABPUR PIPED WATER SUPPLY SCHEME BLOCK- CHANDITALA-I, DISTRICT: HOOGHLY , SM/12239 New Adhoc payment to WBSEDCL against service connnection. BILL/01122/2023-2024 null 28/06/2023 WBSEDCL 105.92 0.00 0 0
4 HOOGHLY Chanditala - I Electrical NABABPUR PIPED WATER SUPPLY SCHEME BLOCK- CHANDITALA-I, DISTRICT: HOOGHLY , SM/12239 New Supply, delivery & installation of submersible pumping machinery and other electrical/ mechanical equipments etc. including allied works for Nababpur water supply scheme, T.W. No.- I & II, Block: Chanditala-I, District- Hooghly under Electrical Division, PHE Dte. ORD/000193/2022-2023 786/ED 09/02/2023 90 M/S P.P. ELECTRICALS 22.36 0.00 0 0
5 HOOGHLY Chanditala - I Hooghly Division NABABPUR PIPED WATER SUPPLY SCHEME BLOCK- CHANDITALA-I, DISTRICT: HOOGHLY , SM/12239 New Material Requisition To Resource Division RTOR000480/2023-2024 3060/17/Hug 11/10/2023 Resource Division 13.96 0.00 0 0
6 HOOGHLY Chanditala - I Hooghly Division NABABPUR PIPED WATER SUPPLY SCHEME BLOCK- CHANDITALA-I, DISTRICT: HOOGHLY , SM/12239 New Acceptance Order for NABABPUR, DUDHKALMI, HARIPUR, JAGMOHANPUR , GANGADHARPUR Piped Water Supply Scheme with.TW, Switch room, boundaryivall, rising main, LDS, FHTC & construction of RCC OHR with 20 mtr. Staging height including soil investigation work at CHANDITALA-I Block under SERAMPORE Sub-Division Under Hooghly Division PHE Dte. Assistant Engineer (Civil) Junior Engineer (Civill) ORD/000318/2023-2024 2393/HUG 10/08/2023 360 GREEN ROYAL INFRA CON PVT LTD 3,243.22 78.37 2.42 9
7 HOOGHLY Chanditala - I Electrical NABABPUR PIPED WATER SUPPLY SCHEME BLOCK- CHANDITALA-I, DISTRICT: HOOGHLY , SM/12239 New Quotation bill for new service connection charges at Nababpur PWSS P.H. No.-I, Hooghly. Application No. 5004064466 Ref ID: 503597309 BILL/00035/2024-2025 21 05/04/2024 WBSEDCL 4.10 0.00 0 null
8 HOOGHLY Chanditala - I Electrical NABABPUR PIPED WATER SUPPLY SCHEME BLOCK- CHANDITALA-I, DISTRICT: HOOGHLY , SM/12239 New Quotation bill for new service connection charges at Nababpur PWSS P.H. No.-I, Hooghly. Application No. 5004064466 Ref ID: 503597309 BILL/00035/2024-2025 21 05/04/2024 WBSEDCL 4.10 0.00 0 null
Total 3,512.64 78.37 2.23