| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 14 | 745.09 | 229.48 | 30.8 | ||||||||||||||
| 1 | HOOGHLY | Haripal | Hooghly Division | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Route Survey, Design Drawing & DPR Preparation of Harat PWSS under Chandannagar Sub - Division, PHE Dte. | Assistant Engineer (Civil) | ORD/000409/2022-2023 | 511/Chan | 29/09/2022 | 15 | ENVIROTECH SOLUTIONS | 4.21 | 4.21 | 100 | 0 | |
| 2 | HOOGHLY | Haripal | Hooghly Division | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Material Requisition To Resource Division | RTOR000200/2022-2023 | 109/ 15/Hug | 10/01/2023 | 0 | Resource Division | 31.12 | 0.00 | 0 | 0 | ||
| 3 | HOOGHLY | Haripal | Hooghly Division | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Material Requisition To Resource Division | RTOR000201/2023-2024 | 1383/5/Hug | 15/05/2023 | 0 | Resource Division | 11.78 | 0.00 | 0 | 0 | ||
| 4 | HOOGHLY | Haripal | Hooghly Division | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Material Requisition To Resource Division | RTOR000399/2023-2024 | 3058/1/Hug | 11/10/2023 | 0 | Resource Division | 116.86 | 0.00 | 0 | 0 | ||
| 5 | HOOGHLY | Haripal | Electrical | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Quotation of New Service Connection for Harat Water Supply Scheme,TW No-II,Block-Haripal, Dist-Hooghly under ED,PHE Dte | BILL/03621/2023-2024 | 224 | 28/08/2023 | 0 | WBSEDCL | 5.57 | 0.00 | 0 | 0 | ||
| 6 | HOOGHLY | Haripal | Electrical | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | New Service Connection at Harat Piped W/S. Sch. TW-II | BILL/02741/2023-2024 | 170 | 09/08/2023 | 0 | WBSEDCL | 3.58 | 0.00 | 0 | 0 | ||
| 7 | HOOGHLY | Haripal | Electrical | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | NEW SERVICE CONNECTION | BILL/02746/2023-2024 | 08/08/2023 | 0 | WBSEDCL | 3.58 | 0.00 | 0 | 0 | |||
| 8 | HOOGHLY | Haripal | Electrical | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Additional Quotation Of New Service Connection for Harat w/s Scheme,PH No-I,Block-Haripal,Dist-Hooghly under ED,PHE Dte | BILL/04079/2023-2024 | 349 | 11/10/2023 | 0 | WBSEDCL | 0.10 | 0.00 | 0 | 0 | ||
| 9 | HOOGHLY | Haripal | Electrical | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Supply, delivery & installation of submersible pumping machinery and other electrical / mechanical equipments etc. including allied works for Harat water supply scheme, T.W. No. I & II, Block: Haripal, District - Hooghly under Electrical Division, PHE Dte. | Assistant Engineer Howrah mechanical Sub Division | Junior Engineer4 | ORD/000083/2022-2023 | 3465/ED | 30/12/2022 | 90 | M/S A.K BANERJEE | 21.49 | 19.62 | 91.3 | 30 |
| 10 | HOOGHLY | Haripal | Hooghly Division | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Construction of 350 cum capacity OHR with 20 mtr. staging height including Soil Investigation work, Laying Distribution System, Rising Main & Interconnection between O.H.R, TW No-I & II, Construction of 1No 5.4 M X 3.6 M Switch Room with Sanitary and Water Supply Arrangements & Boundary Wall at Head Work Site, Construction of 1No 3.6M x 3.0M Switch Room without Sanitary & Water Supply arrangement & Boundary Wall at 2nd T/W Site including Providing FHTC in HARAT Water Supply Scheme at HARIPAL Block under Chandannagar Sub-Division, PHE Dte. | Assistant Engineer (Civil) | Haripal Block junior Enginner | ORD/000618/2022-2023 | 42/HUG | 04/01/2023 | 300 | TITAS CONSTRUCTION | 450.61 | 161.88 | 35.92 | 20 |
| 11 | HOOGHLY | Haripal | Electrical | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Supply, delivery & installation of submersible pumping machinery and other electrical / mechanical equipments etc. including allied works for Harat water supply scheme, T.W. No. III, Block: Haripal, District: Hooghly under Electrical Division, PHE Dte. | Assistant Engineer Howrah mechanical Sub Division | Junior Engineer4 | ORD/002480/2023-2024 | 340/ED | 21/02/2024 | 90 | MOITRA ENGINEERING CO. | 10.74 | 10.44 | 97.21 | 10 |
| 12 | HOOGHLY | Haripal | Hooghly Division | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Sinking of 5 nos. 300 X200 mm dia Tube Well 210 mtr. Depth by D.R. Rig method using UPVC pipe (CD) and UPVC Deep Well Screen (RDS) at Harat& Panrra W/S Scheme under Chandannagar Sub-Division of Hooghly Division, P.H.E. Dte. | Assistant Engineer (Civil) | Junior Engineer (Civill) | ORD/000200/2023-2024 | 1804/HUG | 21/06/2023 | 45 | OSMAN SEKH | 80.84 | 32.51 | 40.22 | 100 |
| 13 | HOOGHLY | Haripal | Hooghly Division | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Making of 2 nos 1.8m X 1.45m X 2.1m KIOSK at Rambati 2nd T/W site & Harat 2nd T/W Site under Chandannagar Sub-Division PHE Dte. | Assistant Engineer (Civil) | Junior Engineer (Civill) | ORD/000937/2023-2024 | 282/Chan | 15/03/2024 | 15 | SUDIPTA SINHA | 0.88 | 0.82 | 93.18 | 100 |
| 14 | HOOGHLY | Haripal | Electrical | HARAT PIPED WATER SUPPLY SCHEME , SM/11290 | New | Quotation of New Service Connection for Harat w/S Scheme,TW No-3 Block-Haripal Dist-Hooghly under ED,PHE Dte. (SM/11290) Application No-5003979859 Reference Id-503541273 | BILL/06474/2023-2024 | 902 | 19/03/2024 | 0 | WBSEDCL | 3.73 | 0.00 | 0 | 0 | ||
| Total | 745.08 | 229.49 | 30.8 | ||||||||||||||