Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
3 93.77 55.62 59.32  
1 NORTH 24 PARAGANAS Barasat Arsenic Division Retrofitting of Chowlpur water supply scheme for providing FHTC under Barasat Arsenic Division, P.H.E. Dte. (Phase - III) , SM/09934 Retrofitting Providing Functional Household Tap Connection (FHTC) and allied works at left out portion of different Mouzas under command area of Chowlpur W/S scheme of Barasat - II blocks from Chowlpur and it adjoining mouzas ground water supply scheme under "JAL SWAPNA" programme under Barasat Arsenic Division, PHE Dte. (Phase - III). Assistant Engineer, HQ-II, Barasat Arsenic Division Junior Engineer ORD/000173/2021-2022 254/B.Ar.D. 17/02/2022 90 MAHMOOD ASSOCIATES PRIVATE LIMITED 81.34 43.28 53.21 1
2 NORTH 24 PARAGANAS Barasat Arsenic Division Retrofitting of Chowlpur water supply scheme for providing FHTC under Barasat Arsenic Division, P.H.E. Dte. (Phase - III) , SM/09934 Retrofitting Repair & Renovation of Iron Elimination Plant of 69 M3 including Media Change of Chowlpur Water Supply Scheme under Barasat - II Block under Barasat Arsenic Division, PHE Dte. Assistant Engineer, HQ-II, Barasat Arsenic Division Junior Engineer ORD/000049/2022-2023 1352/B.Ar.D 22/07/2022 30 WATERCOMP INDIA 4.74 4.71 99.37 1
3 NORTH 24 PARAGANAS Barasat Arsenic Division Retrofitting of Chowlpur water supply scheme for providing FHTC under Barasat Arsenic Division, P.H.E. Dte. (Phase - III) , SM/09934 Retrofitting Restoration due to laying of various dia UPVC/HDPE Pipe distribution line at Malrameswarpur mouza of Chowlpur W/S Scheme under Barasat -II block under Barasat Arsenic Division, PHE Dte. Assistant Engineer, HQ-II, Barasat Arsenic Division Junior Engineer ORD/000204/2023-2024 3030/B.Ar.D. 29/12/2023 30 SIRCON ENGINEERING SERVICES 7.69 7.63 99.22 100
Total 93.77 55.62 59.31